Plasterer Terms and Conditions SA: Plastering Contracts and Quotes
Plasterer terms and conditions in South Australia
Plaster goes onto walls and ceilings that other trades built, and it shows every movement in the structure behind it. When a crack opens a year after handover, the owner sees the plaster first and calls the plasterer. Plastering is building work under the Building Work Contractors Act 1995 (SA), so the licence rules, the homeowner contract rules and the statutory warranties all reach a plastering business. Talon Legal drafts plasterer terms and conditions, plastering contracts and quote terms for South Australian plasterers. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Plasterer terms and conditions SA key facts
| Issue | Position for plasterers in South Australia |
|---|---|
| Governing law | Building Work Contractors Act 1995 (SA) and Regulations 2026; Building and Construction Industry Security of Payment Act 2009 (SA); Australian Consumer Law. Current to 22 November 2026. |
| Plastering | Part of constructing, altering, repairing or improving a building, so it is building work (section 3). |
| Licence | A building work contractors licence to carry on a plastering business for others (section 6(1)); a licence can carry conditions that limit the work (section 7). |
| Without a licence | No fee or other consideration under or in relation to the contract, unless a court finds the failure resulted from inadvertence only (section 6(2)). |
| Homeowner jobs under $20,000 | Minor domestic building work: the statutory warranties apply, the Division 1 contract rules do not (section 27(2); regulation 4(4)). |
| $20,000 or more | A written contract with Form 1 (section 28), a deposit of no more than 5% (section 30(4)) and cooling-off (section 36). |
| Warranties | Proper work to accepted trade standards and good and proper materials (section 32(2)(a), (b)); a term that excludes them is void (section 42). |
| Owner's choice | A deficiency from instructions the owner insisted on against the plasterer's written advice is a defence (section 32(7)). |
| Work for builders | A subcontract; payment claims under the Security of Payment Act (section 13). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need plasterer terms and conditions? What this guide covers
This guide covers what is particular to plasterer terms and conditions in South Australia, current to 22 November 2026: the licence for plastering work, what a plastering quote has to state, cracking from movement in the structure, patching and repairs in older homes, drying and handover, and plastering for builders. The rules plasterers share with tilers, painters and carpenters are in the finishing trades contracts SA guide.
We act for solid plasterers, patch and repair plasterers working in older homes, and plastering contractors who work for builders and renovators.
Free Consultation. Send us your plastering quote and terms, or the subcontract a builder has asked you to sign. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- Does a plasterer need a builders licence?
- What a plastering quote should state
- Who answers for cracked plaster?
- Patching and repairs in older homes
- Drying, painting and handover
- Plastering for builders
- What the plastering pack holds
- How similar matters tend to play out
- Plastering case law
- How we build plasterer terms and conditions
- Frequently asked questions
- Related trade contract guides
Does a plasterer need a builders licence?
Yes, for a business that plasters for others. Plastering forms part of constructing, altering, repairing or improving a building, which is building work (section 3), and a business that performs building work for others needs a building work contractors licence (section 6(1)). A small patching job is a repair to a building, so the size of the job does not take it outside the Act.
The penalties are set out in section 6(1). For an individual, the maximum is $100,000 for a first or second offence, and $150,000 or 12 months imprisonment, or both, for a later one. For a company, the maximum is $500,000 for a first or second offence and $550,000 for a later one. The civil consequence can cost more: a plasterer who should have been licensed is not entitled to any fee or other consideration under or in relation to the contract unless a court finds the failure resulted from inadvertence only (section 6(2)).
Two checks belong in every plastering business:
- The licence holder. Where a company trades, the company needs the licence. A director’s own licence does not authorise the company’s work. The plasterboard fixer guide discusses a ceilings and linings company whose adjudication determination was quashed for that reason.
- Licence conditions. A licence can carry conditions that limit the work it covers (section 7), and the Regulations describe the kinds of work a licence can cover (Schedule 1 Part 3). A plasterer whose licence is limited to subcontract work for licensed builders is outside it when a homeowner engages the business directly.
What a plastering quote should state
A plastering quote is the first document the client reads and the one a court reads first in a dispute. On a homeowner job of $20,000 or more, the contract itself must set out all its terms, carry the licensed name and licence number, be signed by both parties and go to the owner with Form 1 (section 28). Under $20,000 the formalities do not apply, but the quote still records what the plasterer agreed to do.
| Item in the quote | What it settles |
|---|---|
| Walls and ceilings by room | The area the price covers, measured from the plans or on site |
| The substrate | Brick, block, existing plaster or board, and its condition as seen at the quote |
| Coats and finish | The number of coats and the finish the price allows for |
| Making good | Around windows, doors, switches and services, and who removes and refits fittings |
| Control joints | Where they go, or the plasterer's written recommendation that they be installed |
| Hidden conditions | A rate for drummy or failed plaster found once work starts, measured and signed off before it is removed |
| Drying | The drying time before painting, and that painting is not included unless stated |
| Exclusions | Cracking from movement in the structure, damp from leaks or rising damp, and work by other trades |
A variation is part of the contract (section 3). Extra rooms or a change from patching to full replastering can take a job over $20,000, and the contract then has to meet Division 1. Where a homeowner job is $20,000 or more, the deposit cannot exceed 5% of the price, and later payments must be genuine progress payments for work already performed (section 30(1), (4)).
Who answers for cracked plaster?
Plaster cracks for reasons that have nothing to do with the plastering: footings that settle, slabs that shrink, frames that move with the seasons. The statutory warranties are about the plasterer’s own work. They require that the work be performed in a proper manner to accepted trade standards and that materials the contractor supplies be good and proper (section 32(2)(a), (b)). A term that excludes those warranties is void (section 42), so the terms do their work by describing the job rather than by disclaiming it.
The two judgments discussed below show the pattern. In Cirocco Constructions, an arbitrator found that a builder had built stair walls to the contract drawings, which showed no control joint, and that the cracking came from differential movement in the structure ([1854]). The builder had recommended a control joint with a decorative moulding, and the owner had refused the architect’s advice to accept it ([1865]). In Simionato, settlement of the footings cracked two houses; for one of them the Court accepted that underpinning was not necessary and that the house could be repaired by plastering and painting ([166]).
Terms that deal with cracking record three things:
- The cause the price assumes. The plaster is applied to the structure as it stands, and the quote excludes cracking caused by movement of the structure.
- The advice given. A written recommendation for a control joint, or a written warning that the walls show signs of movement, signed or acknowledged by the client.
- The owner’s instruction. Where the owner insists on a course the plasterer advised against in writing, the deficiency that follows from it is a defence to a warranty claim (section 32(7)).
When a client says the plaster has failed. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Patching and repairs in older homes
Repair work in an older house carries a risk new work does not: nobody knows the state of the plaster until it is opened up. The quote should say whether the job is selective patching or a full replaster, because the two are different scopes of work with different prices.
In Cirocco, the building contract allowed a prime cost sum of $1,500 for selective patching and repairs to the internal walls of a church hall, not for their complete replacement, and the instructed repairs went over that sum ([1920]). The experts agreed that the cracking was likely to continue over time ([1921]). The only costing the owner produced was for removing and reinstating all of the plaster, a different scope of work, and the owner failed to prove the cost of the repairs actually required ([1924], [1931]).
For patching work, the terms should state:
| Term | Why it matters |
|---|---|
| Selective patching or full replaster | A different scope of work, priced differently |
| A provisional allowance | The sum allowed for patching, and the rate for work beyond it |
| Matching | That new plaster will not match an old finish exactly unless the whole wall is redone |
| Hidden defects | How failed plaster, old wiring chases and damaged lath found during work are priced |
| Continuing movement | That cracks may re-appear where the structure keeps moving |
Drying, painting and handover
The plasterer’s finish is the painter’s substrate. Paint applied to plaster that has not dried can fail, and the painter and the plasterer then point at each other. The terms should state the drying time the plaster needs, that the client or the painter is to allow it, and that the plasterer is not responsible for paint applied before then.
- Inspection. A handover inspection of each room, with the client’s sign-off on the finish before the painter starts.
- Protection. Who protects floors, joinery and fittings during the work, and who cleans up.
- Other trades. That damage caused after handover by electricians, carpenters or painters is not a plastering defect.
- Warranty period. Proceedings on a statutory warranty must be brought within five years after completion of the work (section 32(5)).
Plastering for builders
Plastering for a builder is a subcontract, not a domestic building work contract (section 3). The Security of Payment Act covers construction work, which includes the construction, alteration and repair of buildings (section 5(1)(a)). A plastering subcontractor that is owed a progress payment can serve a payment claim.
- The claim. It must identify the work, state the amount claimed and say that it is made under the Act (section 13(2)).
- The reply. A builder that does not provide a payment schedule within the time in the subcontract, or 15 business days if that is earlier, becomes liable for the claimed amount (section 14(4)).
- Pay when paid. A clause making payment depend on the builder being paid by the owner has no effect (section 12).
- Homeowners. The Act does not apply to domestic building work for an owner who lives, or proposes to live, in the premises (section 7(2)(b)).
A licensed builder must not contract with an unlicensed person to carry out building work on its behalf (section 47A), so builders will ask for the plastering business’s licence details. The subcontract should also deal with back charges for cracking that appears after the plasterer has left the site, and require written notice and a chance to inspect before any back charge is made.
Before you sign a builder’s subcontract. Book a same-day free 30-minute consultation or call (08) 7094 2021.
What the plastering pack holds
A plastering pack is built from our masters and a plastering schedule, and quoted as a fixed fee before we start.
- Homeowner terms for jobs under $20,000 and a domestic building work contract with Form 1 for larger jobs.
- A quote template that records the substrate, coats, finish, control joints and drying time.
- A patching schedule with a provisional allowance and rates for hidden defects.
- A written advice form for control joints and signs of movement, with the client’s acknowledgement.
- A subcontract with payment claim and schedule procedures and a back charge notice clause.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Every job turns on its own contract and facts.
The crack along the stair. A plasterer finishes a two storey renovation. Eight months later a horizontal crack opens where the upper floor meets the stair wall. The plasterer’s quote excluded cracking from structural movement, and its written note recommending a control joint at that junction is on the file with the owner’s signature.
The patching job that grew. A quote for patching three rooms in a villa allowed a set sum. Once the old plaster comes off, half of the hallway wall is drummy. The quote’s rate for failed plaster, measured and signed off before removal, turns the extra work into a priced variation.
The paint that peeled. A painter starts two days after the plasterer finishes, against the drying time stated in the plasterer’s handover sheet. When the paint fails, the handover sheet shows the plaster was handed over with that drying time recorded.
Plastering case law
None of the decisions below concerned a claim against a plastering business. Each turned on cracked plaster and the question of who answered for it.
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Cirocco Constructions Pty Ltd v Clarke (No 4) [2024] SADC 150 | District Court | Cracking from differential movement in walls built to drawings without a control joint was not the builder's defect; a selective patching allowance did not support a claim costed as full replacement | [1854], [1865], [1866], [1920], [1924], [1931] |
| Simionato v City of Tea Tree Gully [2004] SADC 93 | District Court | A house cracked by footing settlement did not need underpinning and could be repaired by plastering and painting | [164], [166], [171], [209] |
Case notes
Cirocco Constructions Pty Ltd v Clarke (No 4) [2024] SADC 150
A builder’s claim against the owner of a house, with the architect joined, went in part to an arbitrator, whose award the District Court then considered. The arbitrator found that the builder had built the stair walls in accordance with the contract drawings, which provided no horizontal control joint where the upper floors met the walls, and that the cracking resulted from differential movement that a control joint could have mitigated ([1854]). Judge Thomas noted that the owner had refused the architect’s advice to accept the builder’s recommendation of a control joint with a decorative moulding ([1865]), and accepted that the remedial work would be a variation for which the builder would be entitled to an adjustment of the price, so the owner could not establish loss ([1866]). For the church hall, the contract allowed a prime cost sum of $1,500 for selective patching and repairs ([1920]); the only costing produced was for a different scope of work, and the owner failed to prove any relevant measure of remedial costs ([1924], [1931]).
Simionato v City of Tea Tree Gully [2004] SADC 93
The owners of two houses sued over footing settlement and cracking. Judge Herriman found that the settlement and the cracking had returned to a point beyond which substantial improvement was unlikely without mechanical intervention ([164]). For the first house, underpinning was not necessary: “They can be repaired by plastering and painting” ([166]), and repair costs of $20,108 were recoverable ([209]). For the second, two experts considered that a repair by the method a third expert proposed would leave the house liable to distress from seasonal factors, which he disputed ([171]). On appeal, the Full Court dismissed the appeal against the award for the first house and reduced the award for the second, an investment property (State of SA v Simionato [2005] SASC 412 at [101], [103]).
How we build plasterer terms and conditions
We start with how you quote and where your work comes from: homeowners, renovators, builders or insurers.
| Stage | What happens | What we do |
|---|---|---|
| 1. Intake | A questionnaire on your licence, job sizes, substrates and clients | We sort your jobs into minor work, Division 1 contracts and subcontracts |
| 2. Review | Your quotes, terms, handover sheets and any cracking complaints | We mark the scope, exclusion and payment terms that leave you exposed |
| 3. Drafting | Masters and the plastering schedule | We draft homeowner terms, a contract for larger jobs, the patching schedule and a subcontract |
| 4. Delivery | Word documents ready for quoting | We brief you on written advice, drying times and variations |
We cannot promise that terms prevent every dispute. Terms that record the substrate, the advice given and the cause the price assumes settle the cracking argument before it starts.
Before your next plastering quote goes out. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Frequently asked questions
Is a free plastering contract template enough in SA?
Not on its own. A template that is not written for South Australian plastering work can leave out what a homeowner contract of $20,000 or more must contain, such as the licence number, Form 1 and the 5% deposit limit, and can try to exclude the statutory warranties, which is void (Building Work Contractors Act sections 28, 30, 42). It also says nothing about control joints, hidden defects or drying times.
Does a plasterer need a licence for small patching jobs?
Yes, where the business plasters for others. A patching job is a repair to a building, which is building work, and the licence requirement does not depend on the size of the job (Building Work Contractors Act sections 3, 6(1)).
Who pays when plaster cracks after handover?
It depends on the cause. The warranties cover the plasterer’s own work: proper work to accepted trade standards and good and proper materials (Building Work Contractors Act section 32(2)(a), (b)). Cracking caused by movement in the structure is a different question, and the quote and the written advice on file decide much of it.
Can a plastering contract exclude the statutory warranties?
No. Any purported exclusion, limitation, modification or waiver of a right conferred, or a warranty implied, by the Building Work Contractors Act is void (section 42). The contract can define the scope of the work and record the advice the plasterer gave.
What if the owner refuses a control joint?
The plasterer should give the recommendation in writing. It is a defence to a warranty claim that the deficiency arose from instructions the owner insisted on contrary to the contractor’s written advice (Building Work Contractors Act section 32(7)).
Does a plastering job over $20,000 need Form 1?
Yes, for a homeowner. A domestic building work contract of $20,000 or more must be in writing, set out all its terms, carry the licensed name and number, be signed and be given to the owner with Form 1 (Building Work Contractors Act section 28).
How much deposit can a plasterer take?
On a homeowner job of $20,000 or more, no more than 5% of the price; later payments must be genuine progress payments for work already performed (Building Work Contractors Act section 30(1), (4)).
Can a plasterer make a payment claim against a builder?
Yes. Plastering a building is construction work under the Security of Payment Act (section 5(1)(a)), and a claim that meets section 13(2) can be served. A builder that does not provide a payment schedule in time becomes liable for the claimed amount (section 14(4)).
How long is a plasterer liable for defects?
Proceedings on a statutory warranty must be brought within five years after completion of the work (Building Work Contractors Act section 32(5)).
Do I need a lawyer for plasterer terms and conditions?
The law does not require one, but plastering terms have to work with the licence rules, the statutory warranties and the payment claim rules. We draft plasterer terms and conditions for South Australian plastering businesses that put the substrate, the advice and the cause of cracking on paper.
Related trade contract guides
Related guides
- Finishing trades contracts SA
- Plasterboard fixer terms and conditions SA
- Ceiling fixer terms and conditions SA
- Painter terms and conditions SA
- Renovation builder terms and conditions SA
- Heritage builder terms and conditions SA
- Statutory warranties and defects
- Minor domestic building work under $20,000
- Variations to a building contract
- Builders licence SA
- Trade contracts SA