Heritage Builder Terms and Conditions SA: Contracts for Heritage and Restoration Work
Heritage builder terms and conditions in South Australia
Restoration work prices the unknown. Nobody knows what is behind a century of render until it comes off, the stone or brick has to match what is there, and heritage controls decide what may be done at all. Talon Legal drafts heritage builder terms and conditions, cost-plus restoration contracts and approval conditions for South Australian heritage and restoration builders. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Heritage builder terms and conditions SA key facts
| Issue | Position for heritage and restoration builders in South Australia |
|---|---|
| Governing law | Building Work Contractors Act 1995 (SA) and Regulations 2026; Planning, Development and Infrastructure Act 2016 (SA). Current to 21 November 2026. |
| State heritage places | Demolition, removal, conversion, alteration or painting of, or addition to, the place, or other work that could materially affect its heritage value, is development (Planning, Development and Infrastructure Act section 3(1)). |
| Local heritage places | Work, including painting, that could materially affect heritage value is development where the Planning and Design Code specifies it (section 3(1)). |
| Approval first | No development may be undertaken unless it is an approved development (section 101). |
| Cost-plus pricing | Actual cost of the materials and work specified in the contract plus no more than 15% (Building Work Contractors Act section 29(5); regulation 19(1)), for contracts of $20,000 or more. |
| Defects time limit | Five years after completion for statutory warranty claims (section 32(5)), which the 10-year planning long stop does not displace (Duncan at [3]). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need heritage builder terms and conditions? What this guide covers
This guide covers what is particular to heritage builder terms and conditions in South Australia, current to 21 November 2026: heritage approvals, cost-plus and estimate pricing for work nobody can see yet, salvaged and matched materials, owner instructions against advice, hidden fabric, getting paid and defects that surface years later. The rules shared by every builder are in the builder contracts SA guide.
We act for heritage builders, stonemasons, restoration carpenters and conservation contractors.
Free Consultation. Send us your restoration quote, your pricing schedule or a job that has outgrown its estimate. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- Heritage approval: whose job, and what it covers
- Pricing the unknown: cost-plus within the 15% cap
- Old fabric, salvaged materials and owner instructions
- Hidden conditions and variations
- Getting paid on restoration work
- What the heritage pack holds
- How similar matters tend to play out
- Heritage building case law
- How we build heritage builder terms and conditions
- Frequently asked questions
- Related trade contract guides
Heritage approval: whose job, and what it covers
Development includes building work, and the Planning, Development and Infrastructure Act adds heritage work to the definition (section 3(1)).
| Place | What counts as development |
|---|---|
| State heritage place | The demolition, removal, conversion, alteration or painting of, or addition to, the place, or any other work that could materially affect its heritage value |
| Local heritage place | Any work, including painting, that could materially affect the heritage value of the place, of a kind the Planning and Design Code specifies |
| Any building | Building work |
No development may be undertaken unless it is an approved development (section 101). A person must not undertake development contrary to the Act or to a development authorisation, with a maximum penalty of $120,000 and a default penalty of $500 (section 215). On a reading of section 215, the builder who carries out unapproved work undertakes the development, so the risk is not the owner’s alone.
The contract should name who applies for approval, make the approval a condition of starting the affected work, attach the approved plans and conditions, and treat any change the approval requires as a variation.
Pricing the unknown: cost-plus within the 15% cap
A domestic building work contract of $20,000 or more must state a specific price that is fixed and not subject to change, and the terms of payment, subject to the rest of the Division (section 29(1)). Section 29 sits in Division 1 of Part 5, which does not apply to minor domestic building work (section 27(2)).
- Cost-plus items. The contract may provide for the actual cost of materials and work specified in the contract, plus an additional amount of no more than 15% (section 29(5); regulation 19(1)). The items have to be specified: cost-plus cannot cover the whole job by default.
- Hourly rates. An hourly rate applied to the work actually performed is permitted, if the contract specifies the rate (regulation 19(2)).
- The label. A price that may change or is an estimate must carry “This Price May Change” or “Estimate Only” immediately beside or below it (section 29(6)).
- One list. Where there is more than one such price, they go in a single list (section 29(7)), and an estimate must be fair and reasonable (section 29(8)).
- The offence. Breaching section 29 carries a maximum penalty of $50,000 for a natural person and $250,000 for a body corporate (section 29(9)).
Restoration jobs can combine the two: a fixed price for the scope that can be seen, and specified cost-plus items for opening up, repairing hidden fabric and matching stone, brick or joinery.
Old fabric, salvaged materials and owner instructions
The warranty on materials covers “all materials to be supplied by the contractor” (section 32(2)(b)). On a reading of that paragraph, salvaged bricks, reclaimed timber or stone supplied by the owner sit outside it, so the contract should record who supplies each material and in what condition.
Owners of old buildings can have firm views on method. Where the deficiencies complained of arose from instructions the owner insisted on contrary to the builder’s written advice, the builder has a defence (section 32(7)). The advice must be in writing, so the contract should require it and keep it on the job file.
The other warranties apply in the usual way: work in a proper manner to accepted trade standards and in accordance with the agreed plans and specifications, compliance with statutory requirements, and reasonable diligence where no completion period is stipulated (section 32(2)(a), (c), (d)).
Hidden conditions and variations
Restoration disputes turn on work nobody priced. The contract should say how hidden conditions are dealt with before the first wall is opened:
- Investigation. An allowance for opening up and investigating, priced as a specified cost-plus item.
- Notice. A written notice to the owner describing what was found, the options and the price of each, before the work is done.
- Written variation. Work proceeds on the owner’s written instruction. A domestic building work contract includes its variations (section 3), so the price, the approval position and the payment rules move with them.
Written variation clauses are enforced. In Cirocco, below, a contract that confined price adjustments for variations to written instructions left no room for a quantum meruit claim to override it.
Getting paid on restoration work
- Domestic work. On a contract of $20,000 or more, a deposit of no more than 5% and progress payments only for work already performed (section 30(1), (4)), requested in writing where the Security of Payment Act does not apply (section 30(3)).
- Cost-plus claims. Claim the actual cost with the records behind it, and the margin at no more than the percentage the contract states, within the 15% cap.
- Buildings that are not houses. Part 5 applies to domestic building work, which is work in relation to a house (section 3). A church, shopfront or office is not a house, so Part 5 does not apply, while the licence requirement (section 6(1)) and the Building and Construction Industry Security of Payment Act 2009 (SA) still do.
- Owners who do not live there. The Security of Payment Act excludes domestic building work only on premises the party for whom it is done lives in or proposes to live in (section 7(2)(b)).
What the heritage pack holds
A heritage pack is built from our masters and a heritage schedule, and quoted as a fixed fee before we start.
- Heritage builder terms with an approval condition and the approved plans attached.
- A pricing schedule that separates fixed price work from specified cost-plus items, with the single list of estimates.
- A hidden conditions notice and a written variation form.
- A materials register recording who supplies salvaged and matched materials.
- A written advice form for methods the owner insists on.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Every job turns on its own contract and facts.
The colour that needed approval. An owner of a State heritage place asks for the facade to be repainted in a new colour scheme. Painting the place is development (section 3(1)), so the work waits for approval. The terms make approval a condition of that item and keep the rest of the job moving.
The stone that ran out. Matching sandstone is scarce and costs far more than the allowance. The contract listed stone supply as a specified cost-plus item marked “Estimate Only”, so the builder recovers the actual cost plus the stated margin, within the 15% cap.
The crack in year six. Cracking appears in restored masonry six years after completion. A statutory warranty claim had to be brought within five years after completion (section 32(5)), and on Duncan the 10-year planning long stop does not extend that period.
Heritage building case law
Cirocco arose from a house project that involved sandstone and heritage masonry. Duncan concerned defects claimed against a builder by later owners of a house.
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Cirocco Constructions Pty Ltd v Clarke (No 4) [2024] SADC 150 | District Court | Where a domestic building contract confines price adjustments for variations to written instructions, a quantum meruit claim cannot override that allocation of risk | [54], [127], [319], [989], [993] |
| Duncan v Bert Farina Constructions Pty Ltd [2024] SASCA 67 | Court of Appeal | The 10-year planning long stop does not displace the five-year limit for statutory warranty claims; a builder may rely on the shorter period | [3], [141] |
Case notes
Cirocco Constructions Pty Ltd v Clarke (No 4) [2024] SADC 150
The project included remediation of sandstone and heritage masonry: the owner dealt with a heritage stone restorer over acid over-spray and the replacement of discoloured stones ([54]), and heritage masonry specialists gave evidence ([127]). The contract gave the builder no obligation to perform variation works, and no automatic right to a price adjustment, without a written instruction ([319]). The District Court held there was no room for a quantum meruit claim to override that agreed allocation of risk ([989], [993]).
Duncan v Bert Farina Constructions Pty Ltd [2024] SASCA 67
Later owners of a house sued its builder for defects under the statutory warranties. The Court of Appeal held that section 73 of the Development Act 1993 and section 159 of the Planning, Development and Infrastructure Act 2016 operate as a 10-year long stop that does not displace the five-year limit in section 32(5), and that a builder may rely on the shorter period where both apply ([3]). The owners’ appeal was dismissed ([141]).
How we build heritage builder terms and conditions
We start with the building, the approvals it needs and how much of the job nobody can price yet.
| Stage | What happens | What we do |
|---|---|---|
| 1. Intake | A questionnaire on your licence, the places you work on, your pricing methods and your suppliers of salvaged materials | We sort your work into fixed price scope, specified cost-plus items and approval-dependent work |
| 2. Review | Your quotes, estimates, variation forms and past disputes | We mark prices that need the section 29 labels and clauses that leave hidden work unpriced |
| 3. Drafting | Masters and the heritage schedule | We draft your terms, pricing schedule, hidden conditions notice and advice form |
| 4. Delivery | Word documents and a materials register | We brief you on approvals, the 15% cap and written variations |
We cannot promise that terms prevent every dispute. Terms that match how you price and restore old buildings decide most of them before they start.
Before your next restoration quote goes out. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Frequently asked questions
Does heritage building work need approval before it starts?
Work on a State heritage place that alters, paints or adds to it, or could materially affect its heritage value, is development (Planning, Development and Infrastructure Act section 3(1)), and no development may be undertaken unless it is approved (section 101).
Is repainting a heritage building development?
For a State heritage place, painting is in the definition of development (section 3(1)). For a local heritage place, work including painting is development where the Planning and Design Code specifies it (section 3(1)).
Can a heritage builder use a cost-plus contract in SA?
Yes, for materials and work specified in the contract, at actual cost plus no more than 15% (section 29(5); regulation 19(1)), with the price marked “This Price May Change” or “Estimate Only” (section 29(6)).
What is the maximum margin on a cost-plus building contract in SA?
The additional amount cannot exceed 15% of the actual cost of the specified materials and work (section 29(5); regulation 19(1)).
Can I charge an hourly rate for restoration work?
Yes, if the contract specifies the rate: an hourly rate applied to the work actually performed is a permitted cost-plus provision (regulation 19(2)).
What if the owner insists on a method I have advised against?
Section 32(7) gives the builder a defence where the deficiencies arose from instructions the owner insisted on contrary to the builder’s written advice. The advice has to be in writing.
Does the Building Work Contractors Act apply to heritage churches and shops?
The licence requirement does (section 6(1)). Part 5 applies to domestic building work, which is work in relation to a house (section 3), so a church, shop or office is outside Part 5.
How long is a heritage builder liable for defects?
Statutory warranty claims must be brought within five years after completion (section 32(5)). The Court of Appeal held in Duncan that the 10-year planning long stop does not displace that period ([3]).
Do I need a lawyer for heritage builder terms and conditions?
The law does not require one, but heritage work combines approval risk with prices nobody can fix in advance. We draft heritage builder terms and conditions for South Australian restoration builders that fit both.