New Home Builder Terms and Conditions SA: New Home Building Contracts
New home builder terms and conditions in South Australia
A contract to build a new house for an owner in South Australia sits under all of Part 5 of the Building Work Contractors Act 1995 (SA) at once: the section 28 formalities and Form 1, the fixed price rules, the deposit and progress payment limits, building indemnity insurance before work starts, cooling-off, and a warranty that the finished house will be reasonably fit for human habitation. Talon Legal drafts new home building contracts, terms and conditions and trade subcontracts for South Australian builders. Book a same-day free 30-minute consultation or call (08) 7094 2021.
New home builder terms and conditions SA key facts
| Issue | Position for new home builders in South Australia |
|---|---|
| Governing law | Building Work Contractors Act 1995 (SA) and Regulations 2026; Security of Payment Act 2009 (SA); Australian Consumer Law. Current to 20 November 2026. |
| The contract | A domestic building work contract (section 3). At the price of a house, the section 28 formalities apply: every term in writing, the licence details, both signatures, and a copy to the owner with Form 1. |
| Insurance | Where the work needs development approval, a complying building indemnity policy must be in force, and the certificate given to the owner, before any work is performed (sections 33(2), 34). |
| Policy minimums | An excess of not more than $400 and cover of not less than $250,000 per dwelling for policies entered into on or after 10 November 2025 (regulation 20). |
| Deposit | Not more than 5% of the price (section 30(4)), plus prescribed payments such as third-party professional fees, the insurance premium and statutory fees (section 30(2a)). |
| Stage claims | Only genuine progress payments for work already performed, each requested in writing unless the Security of Payment Act applies (section 30(1), (3)). |
| Price | A specific fixed price (section 29(1)). Rise-and-fall only with a stipulated completion period (section 29(2)); cost-plus items at actual cost plus up to 15% (section 29(5); regulation 19(1)). |
| Display homes | Plans and specifications on request, and an implied warranty that a similar house will match the display home, where the builder knows the owner inspected it (section 31). |
| Warranties | Six implied warranties, including that a newly constructed house will be reasonably fit for human habitation (section 32(2)(e)), enforceable for five years after completion (section 32(5)). |
| Cooling-off | Five clear business days after the contract is made, longer if Division 1 or 3 was not complied with (section 36). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need new home builder terms and conditions? What this guide covers
This guide covers what is particular to new home builder terms and conditions in South Australia, current to 20 November 2026: how a new house engages each Division of Part 5, insurance before the first site works, the deposit and stage claims, price and site cost clauses, display homes, handover and defects, and the owners for whom the Security of Payment Act also applies. The rules shared by every builder are in the builder contracts SA guide, and the section-by-section rules for the contract itself are in the domestic building work contracts guide.
We act for volume and project home builders, custom home builders and small builders who build a handful of houses a year.
Free Consultation. Send us the building contract, specification and stage schedule you use now. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- What sets a new home contract apart?
- Insurance before the first site works
- Deposits, stage claims and the final payment
- Price, site costs and variations
- Display homes and the section 31 warranty
- Handover, defects and the habitation warranty
- Owners, investors and the Security of Payment Act
- What the new home pack holds
- How similar matters tend to play out
- New home contract case law
- How we build new home builder terms and conditions
- Frequently asked questions
- Related trade contract guides
What sets a new home contract apart?
Most trade contracts touch one or two Divisions of Part 5. A contract to build a new house touches them all, because the price is well past the $20,000 line for minor domestic building work (regulation 4(4)) and the work is the construction of a house.
| Division of Part 5 | What it requires of a new home contract |
|---|---|
| Division 1, sections 28 to 30 | Written contract with every term set out, the business name, licence number and partners' names and licence numbers, signed by both parties, and a copy given with Form 1; a fixed price with the rise-and-fall and cost-plus limits; the deposit and progress payment rules |
| Division 2, section 32 | Six implied warranties, including the habitation warranty that applies only to the construction of a house |
| Division 3, sections 33 to 35 | Building indemnity insurance where the work needs development approval |
| Division 4, section 36 | The owner's right to cool off |
| Division 5, section 37 | Magistrates Court determination of disputes about whether the work was done in accordance with the contract |
| Division 6, section 38 | Harsh or unconscionable terms can be avoided or modified |
A house is “a building intended for occupation as a place of residence” (section 3), apart from classes the Regulations exclude, such as hotels, motels, hostels and boarding houses. Two new home models need particular care.
- Knock-down rebuilds. Regulation 5(8) takes demolition-only contracts out of Divisions 1, 3 and 4. A single contract to demolish the old house and build the new one is not a demolition-only contract, so, on a reading of regulation 5(8), the whole contract carries the full Part 5 regime.
- House and land packages. The building contract is separate from the land contract and must stand on its own feet under section 28. In Forlyle Pty Ltd v Tiver, discussed below, the Full Court treated a development agreement under which a company was to build a house as a domestic building work contract.
A builder taking on new homes needs a licence whose kind of work covers residential construction of that size (Schedule 1 Part 3 of the Regulations sets out the kinds of work and their limits), an approved registered building work supervisor, and proper supervision of every site (section 12). The builders licence guide covers the classes.
Insurance before the first site works
Division 3 does not apply to work for which development approval was not required, or to minor domestic building work (section 33(2)). Where it applies, a policy of building indemnity insurance that complies with the Act must be in force, and the builder must give the owner a certificate in the prescribed form, before any of the building work is performed (section 34). The maximum fine for a builder that starts without it is $100,000, or $500,000 for a company, with an expiation fee of $20,000.
The Regulations set floors for the policy. The excess cannot be more than $400, and the cover per dwelling cannot be less than $250,000 for policies entered into on or after 10 November 2025, up from $80,000 for earlier policies (regulation 20). Form 2 in Schedule 2 is the certificate.
For a builder, three contract points follow.
- The contract should name who obtains development approval, and treat the insurance certificate as a condition to starting work.
- The site start date should run from the later of approval, the certificate and the owner’s finance approval, not from signing.
- The premium is a prescribed payment, so it can be requested before work starts without being counted as part of the deposit (section 30(2a), (4)).
Deposits, stage claims and the final payment
A builder must not demand a payment under a domestic building work contract unless it is a genuine progress payment for work already performed, or an amount the builder is entitled to under the Security of Payment Act (section 30(1)), or a prescribed payment (section 30(2a)). The prescribed payments include a deposit of not more than 5% of the contract price where the price is $20,000 or more (section 30(4)). On a $480,000 house, that is $24,000.
| Payment | What the Act allows |
|---|---|
| Deposit | Not more than 5% of the price (section 30(4)) |
| Third-party fees, insurance premium and statutory fees | Prescribed payments that can be requested separately (section 30(2a), (4)) |
| Base, frame, lock-up, fixing and similar stages | Genuine progress payments for work already performed (section 30(1)), each requested by written notice unless the Security of Payment Act applies (section 30(3)) |
| Final payment | A progress payment for the completed work, on the contract's completion terms |
The stage names are the industry’s, not the Act’s. What matters is that each stage claim matches work actually done. A stage schedule that front-loads the price, for example a “frame” stage that falls due before the frame is complete, breaches section 30(1), with a maximum fine of $100,000, or $500,000 for a company.
Progress payments a builder has properly received are not ordinarily ordered back. The District Court said in Howland v Michalski [2004] SADC 71 at [30] that repayment generally comes through the harsh or unconscionable terms power in section 38 or a cooling-off termination under section 36, not otherwise. The deposits and progress payments guide sets out the payment rules for every contract size.
Price, site costs and variations
The contract must state a specific price that is fixed and not subject to change, and the terms of payment (section 29(1)). Three tools let a new home contract deal with costs that are not known when it is signed.
- Rise-and-fall. Lawful only if the contract stipulates a period within which the work must be completed (section 29(2)), and limited for work done after that period (section 29(3), (4)).
- Cost-plus items. Specified materials and work can be priced at actual cost plus not more than 15% (section 29(5); regulation 19(1)).
- Estimates. Where an amount may change, such as a provisional sum for rock or site works, it must carry “This Price May Change” or “Estimate Only” beside or below it, all such amounts must be in a single list, and each estimate must be fair and reasonable (section 29(6) to (8)).
Site costs are where new home contracts most often go wrong. A soil report, a contour survey and a check for services before the price is fixed turn most of the unknowns into known costs. What is left should sit in the single list of estimates, with the method of pricing any excess stated.
Variations are part of the contract. A domestic building work contract includes any variation of it (section 3), so, on a reading of sections 3 and 28, a variation should be in writing, set out in full and signed, as section 28 requires of the contract itself. Where a domestic building contract confined price adjustments to variations instructed in writing, the District Court held that the builder could not recover more for unwritten changes through a restitution claim (Cirocco Constructions Pty Ltd v Clarke (No 4) [2024] SADC 150 at [989], [993]). The building variations guide covers the variation process.
Display homes and the section 31 warranty
Display homes are the reason section 31 exists. If a house is, or has been, made available for public inspection to induce people to contract with a builder for similar houses, two rules apply.
- Plans on request. The builder must, on request by a person inspecting the house, make copies of its plans and specifications available for inspection (section 31(1)(a)). The maximum fine for failing to do so is $10,000, with an expiation fee of $3,000 (section 31(2)).
- The display home warranty. A contract made with a person who, to the knowledge of the builder, inspected the house and sought the construction of a similar house is taken to contain a warranty that the new house will be built to the same plans and specifications, and to the same standards of work and materials, as the display home, except to the extent the contract specifically provides for departures (section 31(1)(b)).
The words “to the knowledge of the builder” and “specifically provides” do the work. A sales process that records whether the buyer inspected a display home, and a contract schedule that lists each departure from it, settle most section 31 disputes before they start. In Gupta v Construction Services Australia Pty Ltd, below, the contract’s display home clause was found not to operate because its schedule of departures was blank and the builder had not been told of the inspection.
Handover, defects and the habitation warranty
Every domestic building work contract carries warranties that the work will be done in a proper manner to accepted trade standards and to the agreed plans and specifications, that the builder’s materials will be good and proper, and that the work will comply with all statutory requirements (section 32(2)(a) to (c)). A new home contract carries a further one: if the building work consists of the construction of a house, a warranty that the house will be reasonably fit for human habitation (section 32(2)(e)). On a reading of section 32(2)(e), a renovation or an extension is not the construction of a house, so that warranty does not attach to it.
| Point | The position |
|---|---|
| Time limit | Proceedings for breach of a statutory warranty must start within five years after the work is completed, and the period cannot be extended (section 32(5), (6)) |
| The ten year long stop | The Court of Appeal held that the ten year limits in the planning legislation do not displace the five year limit; both can operate, and a builder may rely on the shorter (Duncan v Bert Farina Constructions Pty Ltd [2024] SASCA 67 at [3]) |
| Later owners | A successor in title to the owner takes the benefit of the warranties (section 32(3), (4)) |
| The owner's own choices | Deficiencies that result from instructions the owner insisted on, contrary to the builder's written advice, are a defence (section 32(7)) |
| Contracting out | Any exclusion, limitation, modification or waiver of the warranties is void (section 42) |
Defects disputes about whether the work was done in accordance with the contract can go to the Magistrates Court (section 37(2), (3)). The Court can order remedial work, to the extent it is practicable for building work to remedy the breach, or payment of an amount due or compensation (section 37(6)). If it thinks the builder is not likely to do the remedial work properly, it can require the builder to engage a licensed building work contractor at its own expense (section 37(7)). A claim over $100,000 can be referred to the District Court on application (section 40).
A handover clause that defines practical completion, provides for a joint inspection and a defects list, and sets a defects period for minor items helps the builder manage defects. It does not cut down the statutory warranties, which run in parallel. The statutory warranties and defects guide goes through each warranty.
Owners, investors and the Security of Payment Act
The Security of Payment Act does not apply to a construction contract for domestic building work on the part of premises that the person for whom the work is done resides in or proposes to reside in (section 7(2)(b)). On a reading of that exclusion, an owner building a home to live in is outside the Act, and an investor building a house to let or sell is inside it. For an investor, the builder can serve payment claims under the Security of Payment Act, and section 30(1) allows a demand for an amount the builder is entitled to under that Act.
The Act applies in full to the builder’s own subcontracts. Trades who build the house serve payment claims on the builder, a builder that does not give a payment schedule within the contract time or 15 business days, whichever expires earlier, becomes liable for the claimed amount (section 14(4)), and a pay when paid clause has no effect (section 12). The subcontractor agreements guide covers the builder’s side.
What the new home pack holds
A new home builder pack is built from our masters and a new home schedule, and quoted as a fixed fee before we start.
- A new home building contract with Form 1 built into the signing process, in versions for owner-occupiers and for investors.
- A stage schedule that ties each claim to identifiable work, and a progress claim notice.
- A single list of estimates for site costs and provisional sums, with “This Price May Change” and “Estimate Only” wording.
- A display home acknowledgement and a schedule of departures from the display home.
- A handover, defects and maintenance procedure, and written advice and variation forms.
- Trade subcontracts with payment claim and payment schedule procedures.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Every job turns on its own contract and facts.
A frame stage claimed early. A builder’s contract makes the frame stage payable when the wall frames are delivered. The frames arrive but are not stood for three weeks. A claim for the frame stage at delivery is not a progress payment for work already performed, so it should wait until the frame is up, and the stage schedule should be redrafted to describe the work, not the delivery.
Rock under the slab. The contract includes a provisional sum of $6,000 for rock excavation, marked “Estimate Only” in the single list of estimates. Rock costs $14,000. The builder recovers the actual cost on the stated pricing method because the estimate was fair and reasonable when made and the contract said how the excess would be priced. Without the provisional sum, the fixed price would carry the loss.
A display home with a different kitchen. The owner inspected the builder’s display home and asked for the same design with a larger kitchen and an extra bedroom. The builder’s sales record notes the inspection and the departures schedule lists the changes. The display home warranty applies to everything else, and the schedule answers the later complaint that the benchtops differ from the display.
New home contract case law
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Gupta v Construction Services Australia Pty Ltd [2014] SASC 16 | Supreme Court | The display home warranty depends on the builder knowing of the inspection and on the house sought being similar; a much-enlarged design was not a similar house | [11], [18], [20] to [24] |
| Duncan v Bert Farina Constructions Pty Ltd [2024] SASCA 67 | Court of Appeal | The ten year planning law limit does not displace the five year limit for statutory warranty claims; a builder may rely on the shorter period | [3] |
| Forlyle Pty Ltd v Tiver [2007] SASC 464 | Full Court | A development agreement to build a house was a domestic building work contract, and a compromise of claims for future defects was void as a waiver of the statutory warranties | [3], [19] |
Case notes
Gupta v Construction Services Australia Pty Ltd [2014] SASC 16
The owners claimed that their new house did not match the display home they said they had inspected before signing. Section 31 applied only if the builder knew of the inspection and the contract was to build a similar house ([11]). The Magistrate found the builder did not know, a finding Kelly J held was open on the evidence ([24]), and found in any event that a design with two extra bedrooms, an extra bathroom, an extra kitchen and a rumpus room was not a similar house ([18]). The contract’s display home clause, whose schedule of departures had been left blank, did not operate because the builder had not been told of the inspection ([20] to [22]). The appeal was dismissed, except that the builder was ordered to connect the rainwater tank to the main toilet as the plans required ([36] and the orders). The section 31 the Court applied had the same operative words as the current section.
Duncan v Bert Farina Constructions Pty Ltd [2024] SASCA 67
The Court of Appeal held that the ten year limits in the planning legislation, section 73 of the Development Act 1993 and section 159 of the Planning, Development and Infrastructure Act 2016 as the Court described them, are a long stop that does not displace the five year limit in section 32(5); both can operate, and a builder sued on the warranties may rely on the shorter period ([3]). The appeal was dismissed ([141]).
Forlyle Pty Ltd v Tiver [2007] SASC 464
The Full Court treated a development agreement under which a company was to build a house as a domestic building work contract ([3]). A settlement that compromised claims for defects not yet known was an exclusion, limitation, modification or waiver of the section 32 warranties, and void under section 42 ([19]); the words reaching unknown claims were severed ([24]).
How we build new home builder terms and conditions
We start with how your business sells and builds: display homes or custom design, owner-occupiers or investors, your stage schedule, how you price site costs and how you hand over.
| Stage | What happens | What we do |
|---|---|---|
| 1. Intake | A questionnaire on your licence, sales process, stage schedule and the owners you build for | We map your process against Divisions 1 to 6 of Part 5 and the Security of Payment Act |
| 2. Review | Your current contract, specification, estimates list and display home paperwork | We mark what fails section 28, 29 or 30, what section 31 exposes and what section 38 or the unfair terms rules would strike out |
| 3. Drafting | Masters and the new home schedule | We draft owner-occupier and investor versions, your stage schedule and your estimates list |
| 4. Delivery | Word documents ready for e-signing with Form 1 | We brief your sales and site teams on Form 1, stage claims, variations and handover |
We cannot promise that a contract prevents every dispute. A contract that matches how you sell and build decides most of them before they start.
Before you sign the next new home contract. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Frequently asked questions
Does a new home builder need a written contract in SA?
Yes. A contract to build a house for an owner is a domestic building work contract, and at any realistic price for a house it is at or above the $20,000 minor work threshold. Section 28 requires it to be in writing, to set out all its terms, to state the licence details, to be signed by both parties and to be given to the owner with Form 1.
How much deposit can a builder take on a new home in SA?
Not more than 5% of the contract price for a contract of $20,000 or more (section 30(4)). Third-party professional fees, the insurance premium and statutory fees are separate prescribed payments (section 30(2a)).
When must building indemnity insurance be in place for a new home?
Before any of the building work is performed, where the work needs development approval (sections 33(2), 34). The builder must also give the owner the certificate before work starts.
Can a builder claim a stage payment before the stage is finished?
No. A progress payment must be a genuine progress payment for work already performed (section 30(1)). A stage claim made before the work it describes is done risks a fine of up to $100,000, or $500,000 for a company.
What is the display home warranty in SA?
Where the builder knows that the owner inspected its display home and sought a similar house, the contract is taken to contain a warranty that the new house will be built to the same plans, specifications and standards, except for departures the contract specifically provides for (section 31(1)(b)).
Does a new house carry a habitation warranty?
Yes. If the building work consists of the construction of a house, the contract carries a warranty that the house will be reasonably fit for human habitation (section 32(2)(e)), in addition to the warranties that apply to all domestic building work.
How long is a builder liable for defects in a new home?
Proceedings for breach of a statutory warranty must start within five years after the work is completed, and the period cannot be extended (section 32(5), (6)). The Court of Appeal has held that the ten year planning law limit does not displace that five year limit.
Can a builder pass on price increases on a new home?
Only through a rise-and-fall clause, which is lawful only if the contract stipulates a completion period, or through cost-plus items or estimates marked as able to change (section 29). Otherwise the price is fixed.
Does the Security of Payment Act apply to a new home?
Not where the owner lives in, or proposes to live in, the house (section 7(2)(b) of that Act). On a reading of that exclusion, it can apply where an investor builds to let or sell. It applies to the builder’s subcontracts with its trades.
Do I need a lawyer for new home builder terms and conditions?
The law does not require one, but a new home contract has to satisfy every Division of Part 5 at once, and an off-the-shelf form does not fit your stage schedule, estimates or display home process. We draft new home building contracts for South Australian builders that fit how you sell and build.
Related trade contract guides
Related guides
- Builder contracts SA
- Renovation builder terms and conditions SA
- Granny flat builder terms and conditions SA
- Kit home builder terms and conditions SA
- Trade contracts SA
- Domestic building work contracts
- Building deposits and progress payments
- Variations to a building contract
- Statutory warranties and defects
- Builders licence SA
- Subcontractor agreements