Underpinning Contractor Terms and Conditions SA: Underpinning and Restumping Contracts
Underpinning contractor terms and conditions in South Australia
An owner who calls an underpinning contractor about cracks wants them to stop. The Building Work Contractors Act 1995 (SA) names underpinning in its definition of building work, so the licence, the homeowner contract rules and the statutory warranties apply. The warranties include fitness for a result the owner makes known, which makes what the contract promises about cracking the centre of the job. Talon Legal drafts underpinning contractor terms and conditions, underpinning and restumping contracts and subcontracts for South Australian underpinning, restumping and re-levelling businesses. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Underpinning contractor terms and conditions SA key facts
| Issue | Position for underpinning contractors in South Australia |
|---|---|
| Governing law | Building Work Contractors Act 1995 (SA) and Regulations 2026; Planning, Development and Infrastructure Act 2016 (SA) and its General Regulations 2017; Work Health and Safety Regulations 2012 (SA); Building and Construction Industry Security of Payment Act 2009 (SA). Current to 21 November 2026. |
| Underpinning as building work | Underpinning a building is named in the definition of building work, and so is repairing a building, which on a reading includes restumping (section 3). |
| At a house | Domestic building work (regulation 4(2)(b)); Division 1 and Form 1 at $20,000 or more (sections 27(2), 28). |
| The result promised | Where the owner makes known the result wanted and relies on the contractor, the work must be reasonably fit to achieve it (section 32(2)(f)). |
| Temporary support | Structural alterations or repairs that need temporary support to prevent collapse are high risk construction work (Work Health and Safety Regulations regulation 291(e)). |
| Next door | A neighbour affected by excavation can require shoring or underpinning to its engineer's specification (Planning, Development and Infrastructure Act section 139; regulation 64(3)). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need underpinning contractor terms and conditions? What this guide covers
This guide covers what is particular to underpinning contractor terms and conditions in South Australia, current to 21 November 2026. It deals with the licence and the $20,000 line, the engineer’s report, existing cracking and the result promised, temporary support and excavation, work next to a neighbour, and payment. The rules every structural trade shares are in the concrete and masonry contracts SA guide.
We act for underpinning and restumping businesses that work for owners, builders, insurers and neighbours.
Free Consultation. Send us the quote, report template or terms you use now. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- The licence and the $20,000 line
- The engineer's report and the scope
- Existing cracks and the result promised
- Temporary support, excavation and safety
- Underpinning next to a neighbour
- Payment, monitoring and handover
- What the underpinning pack holds
- How similar matters tend to play out
- Underpinning case law
- How we build underpinning contractor terms and conditions
- Frequently asked questions
- Related trade contract guides
The licence and the $20,000 line
Building work includes underpinning, altering, repairing or improving a building (section 3), and carrying on a business of performing building work for others needs a licence (section 6(1)). A licence can be limited to specified building work (Schedule 1 Part 3 clause 3(d)).
| Underpinning job | Rules |
|---|---|
| Underpinning or restumping at a house under $20,000 | Minor domestic building work: the statutory warranties in section 32 apply; Division 1 does not (section 27(2); regulation 4(4)) |
| The same job at $20,000 or more | Division 1: a written contract with every term, licence details, signatures and Form 1 (section 28), a fixed price (section 29), a deposit of no more than 5% (section 30(4)), cooling-off (section 36) |
| A job that needs development approval, at $20,000 or more | Building indemnity insurance in force, and the certificate given, before work starts (sections 33(2), 34) |
| Underpinning for a builder | A subcontract, not a domestic building work contract (section 3); the Security of Payment Act |
Whether the work needs development approval decides whether insurance applies (section 33(2)). The contract should say who confirms the approval position before work starts. A variation is part of the contract (section 3), so extra pins or piers found to be needed can take a job over $20,000.
The engineer’s report and the scope
Where an engineer has reported on the movement and designed the scheme, the terms should tie the scope to that design. The statutory warranties require the work to be performed in a proper manner, to accepted trade standards and in accordance with the plans and specifications the parties agreed (section 32(2)(a)).
| Term | What it settles |
|---|---|
| The report | The engineer, the report date, the drawings and the soil information relied on |
| Who engaged the engineer | The owner, the builder or the contractor, and who carries the design |
| The scope | The walls and footings to be underpinned, the number and depth of piers or pins, and any jacking or re-levelling |
| Out of scope | Cracks, walls or footings the report does not address |
| Changes | That more piers, deeper piers or a design change need the engineer's written sign-off and are variations |
A partial scheme carries a risk the owner should understand. If the owner insists on underpinning less than the contractor recommends, the contractor’s advice should be in writing: it is a defence to a warranty claim that the deficiencies arose from instructions insisted on by the building owner contrary to the contractor’s written advice (section 32(7)).
Existing cracks and the result promised
The statutory warranties include fitness for purpose and result. Where the owner has expressly made known the purpose of the work, or the result the owner wants it to achieve, so as to show reliance on the contractor’s skill and judgment, the work and materials must be reasonably fit for that purpose or reasonably expected to achieve that result (section 32(2)(f)).
An owner who tells the contractor the work must stop the cracking may have made a result known, if the owner relies on the contractor’s skill and judgment. The contract should say what the work is designed to do, and what it is not.
- Condition record. Photographs and a crack schedule before work starts, signed by both parties.
- What the work addresses. The footing movement the engineer identified, and the walls the scheme covers.
- What it does not. Movement from other causes the report did not address, such as a later leak, new trees or changes to drainage.
- Cosmetic repairs. Whether patching, plastering and painting are in the price, or left to others.
- Monitoring. Any monitoring period after the work, and how readings are taken and shared.
Not every cracked house needs underpinning. In Simionato, below, the Court was satisfied that underpinning one of the houses was not necessary and that it could be repaired by plastering and painting ([166]). Underpinning was the proposal for the other house, where the footings had been displaced ([169]).
Temporary support, excavation and safety
Underpinning means digging under footings that are carrying a building. The Work Health and Safety Regulations 2012 treat several parts of that work as high risk construction work:
| Work | Source |
|---|---|
| Structural alterations or repairs that require temporary support to prevent collapse | Regulation 291(e) |
| Work in or near a shaft or trench deeper than 1.5 metres | Regulation 291(g) |
| Work in an area of a workplace where powered mobile plant moves | Regulation 291(o) |
A business carrying out high risk construction work must have a safe work method statement prepared before the work starts (regulation 299(1)). A business that excavates a trench at least 1.5 metres deep must minimise the risk of collapse by shoring, benching or battering, unless a geotechnical engineer advises in writing that all sides are safe (regulation 306(3), (4)). Before excavation starts, the person with management or control of the workplace must take all reasonable steps to obtain current underground essential services information (regulation 304(2)).
The contract should price those steps, and say who provides the engineer’s advice and the services information.
Underpinning next to a neighbour
Underpinning work meets the neighbour in two ways.
The neighbour’s excavation. Where a development approval envisages access to other land to deal with an effect on its stability, the person undertaking the development must serve the owner of that land with a notice in the prescribed form at least 20 business days before the work starts (Planning, Development and Infrastructure Act 2016 section 139(2)(a); General Regulations regulation 64(2a)). The neighbour may then require the building owner to shore up any excavation, or to underpin, stabilise or otherwise strengthen the foundations of any building, to the extent the neighbour’s professional engineer specifies (regulation 64(3)). The building owner pays the reasonable cost of that engineer’s report, plans and specifications (regulation 64(4)). An underpinning contractor engaged for that work should know who its client is, who specified the work and who pays.
The contractor’s own excavation. Excavating beside a boundary to underpin a house can itself be work treated as affecting the stability of the neighbour’s land (regulation 64(2)(a)). In Bijok, below, a builder that used a retaining system other than the engineers’ design while excavating next to a boundary was found liable in negligence for the neighbours’ subsidence ([46]).
Where access from the neighbour’s land is needed for building work, a notice can be served under section 140; if there is no response within 10 business days, or access is refused, the Environment, Resources and Development Court can authorise access on conditions (section 140(2) to (5); regulation 64A(2)).
Payment, monitoring and handover
For a homeowner job of $20,000 or more, the contractor must not demand payment unless it is a genuine progress payment for work already performed, a prescribed payment such as a deposit of no more than 5%, or an entitlement under the Security of Payment Act (section 30(1), (2a), (4)). The stages should follow the work: excavation, piers or pins, jacking or packing, and reinstatement.
At handover, the terms should provide for a joint inspection against the condition record, the engineer’s sign-off where the design calls for one, and the start of any monitoring period. Proceedings on a statutory warranty must be brought within five years after completion of the work (section 32(5)).
Underpinning for a builder is a subcontract. The laying of foundations and excavation are construction work under the Security of Payment Act (section 5(1)(e)(i), (ii)), and a payment claim must identify the work, state the amount and say it is made under the Act (section 13(2)).
What the underpinning pack holds
An underpinning pack is built from our masters and an underpinning schedule, and quoted as a fixed fee before we start.
- Homeowner terms for jobs under $20,000 and a domestic building work contract with Form 1 for larger jobs.
- A scope sheet tied to the engineer’s report, with what the work addresses and what it does not.
- A condition record and crack schedule, signed before work starts.
- A written advice form for partial schemes and owner instructions.
- A neighbour clause that follows section 139 and regulation 64.
- A subcontract with payment claim and schedule procedures for work for builders.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Every job turns on its own contract and facts.
The crack that came back. Six months after underpinning the rear wall, a new crack appears in the front bedroom. The scope sheet limited the work to the rear footings in the engineer’s report, and the condition record showed the front crack was already there in a finer form. The dispute is about the front wall, not the scheme.
The partial scheme. The engineer recommends piers along two walls. The owner can afford one wall and insists on it. The contractor’s written advice, signed by the owner, records the risk to the other wall.
The neighbour’s engineer. A developer next door excavates for a basement, and the neighbour’s engineer specifies underpinning of the neighbour’s house. The underpinning contractor is engaged by the developer, and its contract records that the work follows the neighbour’s engineer’s specification and that the developer pays.
Underpinning case law
None of the decisions below concerned an underpinning contractor’s own contract; both concerned damage to houses from ground movement. Each turned on a point an underpinning business can face.
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Bijok v SJ Weir Pty Ltd [2011] SADC 20 | District Court | A builder excavating next to a boundary, using a retaining system other than the engineers' design, was liable in negligence for the neighbours' subsidence | [2], [7], [38], [42], [45], [46], [63] |
| Simionato v City of Tea Tree Gully [2004] SADC 93 | District Court | Underpinning was found unnecessary for one house, which could be repaired by plastering and painting; it was proposed for another where the footings were displaced | [34], [166], [169], [170], [209], [219] |
Case notes
Bijok v SJ Weir Pty Ltd [2011] SADC 20
A builder excavated along a boundary for a basement carport ramp. It needed a temporary retaining structure to stop soil moving from under the neighbours’ land; the wall it built proved inadequate, and subsidence damaged the neighbours’ carport, driveway and house ([7]). The engineers’ design for that section included propping, but the builder used an unpropped method designed for another section ([38]). Judge Boylan said that an owner has a right to support of land in its natural state from adjoining land, which does not extend to a structure unless its weight did not contribute ([42]). The builder, as occupier, owed a duty to take reasonable care that its excavation did not cause foreseeable damage, and breached it ([45], [46]). It was found solely liable ([2]), with damages of $141,952 ([63]).
Simionato v City of Tea Tree Gully [2004] SADC 93
Owners of two houses sued the State in nuisance and negligence over footing settlement, claiming the costs of underpinning and repair ([34], [35]). For one house, Judge Herriman was satisfied that underpinning was not necessary and that it could be repaired by plastering and painting ([166]), and allowed repair costs of $20,108 ([209]). For the other, the proposal was to jack the displaced footings level and fix them in place with underpins ([169]). An expert conceded that the cost of underpinning could reach a point where it became uneconomic compared with demolition and rebuilding ([170]). The owner of that house was allowed $98,000 for the capital loss expected even after underpinning and repairs ([219]).
How we build underpinning contractor terms and conditions
We start with how you assess, scope and underpin: who engages the engineer, what you promise, and who you work for.
| Stage | What happens | What we do |
|---|---|---|
| 1. Intake | A questionnaire on your licence, methods, engineers and clients | We sort your jobs into minor work, Division 1 contracts, neighbour work and subcontracts |
| 2. Review | Your quotes, reports, condition records and terms | We mark the scope, result and payment terms that leave you exposed |
| 3. Drafting | Masters and the underpinning schedule | We draft homeowner terms, a contract for larger jobs, scope and condition forms and a subcontract |
| 4. Delivery | Word documents ready for quoting | We brief your estimators on scope sheets, written advice and handover |
We cannot promise that terms prevent every dispute. Terms that fix the scope, the existing condition and the result promised settle those questions before the first pier goes in.
Before your next underpinning quote goes out. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Frequently asked questions
Is underpinning building work in SA?
Yes. Underpinning a building is named in the definition of building work in the Building Work Contractors Act 1995 (section 3), and carrying on that business for others needs a licence (section 6(1)).
Does an underpinning job need a written contract?
At a house, for $20,000 or more, yes: a contract that meets section 28 of the Building Work Contractors Act 1995, given with Form 1. Under $20,000, the statutory warranties in section 32 still apply.
Does underpinning have to stop all cracking?
Only if that is what the contract promised or the owner made known and relied on. Where the owner makes known the result wanted, the work must be reasonably fit to achieve it (Building Work Contractors Act section 32(2)(f)). The scope sheet should say what the work addresses.
What if the owner wants less underpinning than recommended?
Record the advice in writing. It is a defence that the deficiencies arose from instructions the owner insisted on contrary to the contractor’s written advice (Building Work Contractors Act section 32(7)).
Is underpinning high risk construction work?
It can be. Structural alterations or repairs that need temporary support to prevent collapse are high risk construction work, and so is work near a trench or shaft deeper than 1.5 metres (Work Health and Safety Regulations 2012 regulation 291(e), (g)). A safe work method statement is required (regulation 299(1)).
Can a neighbour require a developer to underpin their house?
It can. Where section 139 of the Planning, Development and Infrastructure Act 2016 applies, the neighbour may require the building owner to underpin, stabilise or otherwise strengthen foundations to the extent its professional engineer specifies (General Regulations regulation 64(3)).
Who pays the neighbour's engineer?
The building owner pays the reasonable cost of the neighbour’s engineer’s report, plans and specifications for that work (General Regulations regulation 64(4)).
Does every cracked house need underpinning?
No. In Simionato, the Court was satisfied that one house did not need underpinning and could be repaired by plastering and painting.
How much deposit can an underpinning contractor take?
For a homeowner job of $20,000 or more, no more than 5% of the price. Later payments can only be genuine progress payments for work already performed (Building Work Contractors Act section 30(1), (4)).
Do I need a lawyer for underpinning contractor terms and conditions?
The law does not require one, but underpinning terms have to work with the builders licence rules, the result warranty, the neighbour provisions and the safety duties. We draft underpinning contractor terms and conditions for South Australian underpinning businesses that put the scope and the promise on paper.
Related trade contract guides
Related guides
- Concrete and masonry contracts SA
- Retaining wall builder terms and conditions SA
- Concreter terms and conditions SA
- Insurance repair builder terms and conditions SA
- Renovation builder terms and conditions SA
- Minor domestic building work under $20,000
- Statutory warranties and defects
- Variations to a building contract
- Builders licence SA
- Trade contracts SA