Building Deposits and Progress Payments SA: How Much a Builder Can Ask For
Building deposits and progress payments in South Australia
A building deposit in South Australia is capped by law. On a home building contract of $20,000 or more, the deposit can be no more than 5% of the price, and every later payment must be a genuine progress payment for work already performed, a prescribed payment or an entitlement under the Security of Payment Act. Demanding more is an offence under section 30 of the Building Work Contractors Act 1995 (SA), with a maximum fine of $100,000 for an individual and $500,000 for a company. Talon Legal drafts payment terms for builders and trades and advises when a payment dispute starts. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Building deposits and progress payments key facts
| Issue | Position in South Australia |
|---|---|
| Governing law | Section 30 of the Building Work Contractors Act 1995 (SA) and the Building and Construction Industry Security of Payment Act 2009 (SA). Current to 20 November 2026. |
| Which contracts | Domestic building work contracts that are not minor domestic building work, and preliminary work contracts collateral to them (sections 27(2), 30(1), (4)). |
| Deposit where the price is $20,000 or more | Not more than 5% of the price, for contracts made on or after 1 September 2011 (section 30(4)(d)(ii)). |
| Deposit where the price is under $20,000 | Not more than $1,000, where the contract is not minor work (section 30(4)(d)(i)). |
| Contracts made before 1 September 2011 | A deposit of not more than $1,000 (section 30(4)(c)). |
| Other payments up front | Payments to third parties for engineering, drawing, surveying or other professional services, and reimbursement of building indemnity insurance or fees payable under an Act (section 30(4)(a), (b)). |
| Progress payments | Only a genuine progress payment for work already performed, or an entitlement under the Security of Payment Act (section 30(1)). |
| Written request | The owner need not make a progress payment unless the contractor has asked for it by written notice, unless the Security of Payment Act applies (section 30(3)). |
| Penalties | Up to $100,000 for an individual and $500,000 for a company; expiation fee $5,000 for the prescribed payment offence (section 30(1), (2a)). |
| Presumption | A contractor proved to have received a payment that was not allowed is presumed to have demanded it, unless it proves otherwise (section 30(2), (2b)). |
| Owners who live there | The Security of Payment Act does not apply to domestic building work on the part of premises the owner resides in or proposes to reside in (section 7(2)(b) of that Act). |
| Subcontractors | Progress payments from each reference date, payment claims, and a payment schedule within the contract time or 15 business days if that is earlier (sections 8, 13 and 14 of the Security of Payment Act). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need payment terms that comply? What this guide covers
This guide sets out the building deposit limits, how much a builder or trade can take before work starts, what can be charged as the job runs, and where the Security of Payment Act takes over, current to 20 November 2026. It is part of our trade contracts SA guides, with the contract formalities in domestic building work contracts and the rules for jobs under $20,000 in minor domestic building work.
We act for builders and trades setting up payment terms, and for both sides when a payment is withheld, a deposit is challenged or a progress claim goes unpaid.
Free Consultation. Send us your contract’s payment schedule before you send the next invoice. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- How much deposit can a builder ask for?
- What else can be charged before work starts?
- What is a genuine progress payment?
- Must progress payments be requested in writing?
- What is a preliminary work contract?
- What are the penalties?
- Where does the Security of Payment Act fit?
- Can an unlicensed contractor claim progress payments?
- Can an owner get progress payments back?
- How similar matters tend to play out
- How we set up payment terms
- Deposit and progress payment case law
- Frequently asked questions
- Related trade contract guides
How much deposit can a builder ask for?
Section 30(2a) of the Building Work Contractors Act 1995 (SA) prohibits a person from demanding or requiring a payment under a domestic building work contract or preliminary work contract unless it is a prescribed payment. A building deposit is one kind of prescribed payment, and its limit depends on when the contract was made and the price it states.
| Contract made | Price stipulated in the contract | Maximum deposit | Provision |
|---|---|---|---|
| Before 1 September 2011 | Any | $1,000 | Section 30(4)(c) |
| On or after 1 September 2011 | Less than $20,000 | $1,000 | Section 30(4)(d)(i) |
| On or after 1 September 2011 | $20,000 or more | 5% of the price | Section 30(4)(d)(ii) |
Section 30 is in Division 1 of Part 5, which does not apply to minor domestic building work (section 27(2)). For contracts made on or after 10 November 2025, work at a cost to the owner of less than $20,000 is minor (Building Work Contractors Regulations 2026, regulation 4(4)(c)). Read together, the $1,000 limit now has practical work mainly for contracts made from 1 September 2011 to 9 November 2025 with a price from $12,000 to under $20,000, and for a contract whose stated price is under $20,000 but whose cost to the owner reaches $20,000 or more.
The Regulations also take some contracts outside section 30 altogether: contracts solely for demolition (regulation 5(8)), work as a contractor for the South Australian Housing Trust or its Minister (regulation 5(10)(a)), and contracts where the building owner is a public company or a subsidiary of one (regulation 5(10)(b)).
On a $480,000 new home the deposit can be up to $24,000. On a $60,000 extension it can be up to $3,000. A contract that labels a larger sum a “booking fee”, “commitment fee” or “materials deposit” does not escape the limit: section 30(2a) applies to any payment that is not a prescribed payment.
What else can be charged before work starts?
Besides the deposit, section 30(4) lists these prescribed payments:
| Prescribed payment | Provision | Example |
|---|---|---|
| A payment to a third party for engineering, drawing, surveying or other professional services | Section 30(4)(a) | The engineer's footing design, the drafter's plans, the surveyor's set-out, paid to those third parties |
| A payment to reimburse the cost of building indemnity insurance | Section 30(4)(b) | The premium for the policy that section 34 requires before work starts |
| A payment of any fee required to be paid under an Act for the work | Section 30(4)(b) | Development application and approval fees |
| A payment of a kind prescribed by the regulations | Section 30(4)(e) | The Building Work Contractors Regulations 2026 read on 20 November 2026 contain no regulation made for this paragraph |
The professional services payment is for a payment to a third party. Fees for the contractor’s own design work are not within paragraph (a) on its words, so a contractor that designs in-house should take advice on how its design fee is structured.
What is a genuine progress payment?
Under section 30(1), a person must not demand or require a payment under a domestic building work contract or preliminary work contract unless it is a genuine progress payment in respect of work already performed, or the person is entitled to the payment under the Security of Payment Act. The maximum penalty is $100,000 for an individual and $500,000 for a company.
Two words in section 30(1)(a) carry the weight: “genuine” and “already”. A progress payment is for work that has been done, not work about to start. A stage schedule that asks for 40% of the price at frame stage when the frame represents a quarter of the work is exposed to the argument that the payment is not a genuine progress payment for work already performed. Stage percentages should track the value of the work completed at each stage.
Section 30(1) and section 30(2a) are separate offences. A deposit within the limit satisfies section 30(2a); every later payment must also pass section 30(1).
Must progress payments be requested in writing?
Yes, for domestic building work contracts to which section 30 applies. Section 30(3) provides that the owner is not obliged to make a progress payment unless the contractor has requested it by notice in writing given to the owner or the owner’s authorised agent, or the contract is one to which the Security of Payment Act applies, in which case that Act’s progress payment provisions apply.
The notice need not be elaborate, but it should identify the stage or work the payment is for, the amount and the contract it is made under. An invoice that does those things will usually serve.
What is a preliminary work contract?
Section 30 also applies to a preliminary work contract: a contract that is collateral to, or otherwise related to, an existing or contemplated domestic building work contract, and that provides for work that is preliminary or ancillary to the domestic building work (section 30(4)).
Site investigations, soil tests, concept drawings and feasibility work done before the main contract is signed can fall within that definition. A contractor that charges a large “design and estimate” fee and later signs the building contract needs that fee to fit within section 30(1) or the list of prescribed payments.
What are the penalties?
| Offence | Maximum penalty | Expiation fee |
|---|---|---|
| Demanding or requiring a payment that is not a genuine progress payment for work already performed or a Security of Payment Act entitlement (section 30(1)) | $100,000 (individual); $500,000 (company) | None stated |
| Demanding or requiring a payment that is not a prescribed payment (section 30(2a)) | $100,000 (individual); $500,000 (company) | $5,000 |
If it is proved that the contractor received a payment of a kind the section does not allow, it is presumed, in the absence of proof to the contrary, that the contractor demanded or required it (section 30(2), (2b)). Section 54 gives a defence where the offence was not committed intentionally and did not result from a failure to take reasonable care.
Payment offences are prosecuted alongside the other Part 5 offences. In Commissioner for Consumer Affairs v Brittain [2007] SASC 381, a $27,000 driveway and carport job led to convictions for demanding an unauthorised payment as well as for working unlicensed, without a written contract and without insurance ([2], [5]).
Where does the Security of Payment Act fit?
The Building and Construction Industry Security of Payment Act 2009 (SA) applies to any construction contract, whether written or oral (section 7(1)). It does not apply to a construction contract for domestic building work on the part of any premises that the party for whom the work is carried out resides in or proposes to reside in (section 7(2)(b)).
That exclusion is narrower than “homeowners”. On a plain reading of section 7(2)(b), domestic building work for a landlord, an investor or a developer who does not live in the premises is outside the exclusion. The Building Work Contractors Act anticipates the overlap: section 30(1)(ab) allows a demand for a payment to which the contractor is entitled under the Security of Payment Act, and section 30(3)(b) applies that Act’s progress payment provisions where it applies. No South Australian decision on the reach of section 7(2)(b) was located.
Where the Security of Payment Act applies, its core payment rules are:
| Rule | Provision |
|---|---|
| A right to a progress payment on and from each reference date | Section 8 |
| A progress payment is due on the date the contract sets or, if it sets none, 15 business days after a payment claim; interest runs on unpaid amounts | Section 11 |
| A pay when paid provision has no effect | Section 12 |
| A payment claim must identify the work, state the amount claimed and state that it is made under the Act | Section 13 |
| A respondent who does not give a payment schedule within the time the contract allows or 15 business days, whichever is earlier, becomes liable for the claimed amount | Section 14 |
| An unpaid claimant can recover the amount as a debt, or apply for adjudication, and can suspend work after notice | Sections 15 to 17 |
Can an unlicensed contractor claim progress payments?
No, unless a court finds the failure to be licensed resulted from inadvertence only. Section 6(2) says a person required to be licensed is not entitled to any fee, other consideration or compensation under or in relation to a contract unless licensed or so excused.
In Tagara Builders Pty Ltd v AP & L Services Pty Ltd [2015] SASC 30, a ceilings and linings subcontractor company that held no licence had obtained an adjudication under the Security of Payment Act. The Supreme Court held that section 6(2) disentitled it to the contract price, so it was not entitled to progress payments under the Security of Payment Act; the adjudicator had no jurisdiction and the determination was void ([51], [52]). The Court also said section 6(2) does not prevent a claim in quantum meruit for the value of the work ([50]).
Can an owner get progress payments back?
Not simply because the owner is unhappy. In Howland v Michalski [2004] SADC 71, the District Court observed that a builder who has received progress payments under the contract is not required, and cannot be ordered, to repay them unless the contract is for domestic building work and a court finds a term harsh or unconscionable under section 38, or the owner has terminated under section 36 ([30]).
Both routes are real. Section 38(4)(c) lets the court order repayment of an amount paid under a term it avoids or modifies. After a cooling-off termination, the Magistrates Court can order the return of the whole or part of what the owner paid, or payment to the contractor for materials and work (section 36(4)). An owner who paid a deposit above the limit, or a progress payment for work not yet done, also has the contractor’s breach of section 30 to rely on.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Each depends on its own contract and facts.
A $72,000 second-storey extension. The builder’s contract asks for a 10% building deposit of $7,200 on signing. The limit is 5%, or $3,600 (section 30(4)(d)(ii)). The demand for the extra $3,600 is an offence under section 30(2a), and because a Division 1 requirement was not complied with, the owner can terminate under section 36 until the work is completed.
A pool builder’s stage schedule. The schedule asks for 35% at excavation, when excavation is a small share of the work. The owner pays, then disputes the next stage. The builder faces the argument that the excavation payment was not a genuine progress payment for work already performed (section 30(1)), and every later claim is read against that history.
A plumbing subcontractor on an investor’s townhouse. The subcontractor works for the builder, so its contract is a subcontract and the Security of Payment Act applies. It serves a payment claim stating that it is made under the Act. The builder must give a payment schedule within the contract time or 15 business days, whichever is earlier, or become liable for the claimed amount (section 14).
How we set up payment terms
Payment terms decide cash flow, and in South Australia they are also a compliance question. We build payment schedules that meet section 30 and, where it applies, the Security of Payment Act.
| Stage | What happens | What we do |
|---|---|---|
| 1. Your jobs | You tell us your job types, sizes and current stage percentages | We test the deposit and each stage against section 30 |
| 2. Schedule | A stage schedule matched to the value of the work at each stage | We draft it and the written request wording for section 30(3) |
| 3. Preliminary work | Design, soil test and estimate fees before the main contract | We structure them to fit section 30 |
| 4. Security of Payment Act | Subcontracts and jobs for owners who do not live there | We draft payment claim and schedule clauses and the forms |
| 5. Disputes | A payment is withheld or a deposit is challenged | We advise on recovery, adjudication, section 36 and section 38 |
We cannot promise every invoice will be paid on time. Compliant payment terms keep the arguments about money on the merits of the work.
Before your next invoice. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Deposit and progress payment case law
These are the South Australian decisions this guide relies on. The case notes state what each court decided.
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Commissioner for Consumer Affairs v Brittain [2007] SASC 381 | Supreme Court | Demanding an unauthorised payment was prosecuted with licence, contract and insurance offences | [2], [5], [21], [22] |
| Tagara Builders Pty Ltd v AP & L Services Pty Ltd [2015] SASC 30 | Supreme Court | An unlicensed contractor is not entitled to Security of Payment Act progress payments; quantum meruit is not barred | [50], [51], [52] |
| Howland v Michalski [2004] SADC 71 | District Court | Progress payments are repayable only through section 38 relief or a section 36 termination | [30] |
Case notes
Commissioner for Consumer Affairs v Brittain [2007] SASC 381
A handyman franchisee quoted $27,000 for a driveway and carport, accepted orally, with no written contract and no licence ([5]). He was convicted on his pleas of guilty of offences including demanding or requiring an unauthorised payment for building work ([2]). Gray J dismissed the Commissioner’s appeal against the single $2,500 fine ([21], [22]). The current maximum for a section 30 offence is far higher than the penalty that applied in 2004.
Tagara Builders Pty Ltd v AP & L Services Pty Ltd [2015] SASC 30
Blue J held that an unlicensed subcontractor, without a court finding of inadvertence under section 6(2)(b), was not entitled to payment of the contract price and therefore not entitled to progress payments under section 13 of the Security of Payment Act, so the adjudication determination was void ([51]) and orders quashing it were made ([52]). His Honour reasoned that section 6 disentitles an unlicensed contractor from recovering the contract price but does not preclude a quantum meruit claim ([50]).
Howland v Michalski [2004] SADC 71
In reviewing a minor civil action about a domestic building contract, the District Court observed that a builder who has received progress payments under the contract is not required, and cannot be ordered, to repay them except where a court finds a term harsh or unconscionable under section 38 or the owner has terminated under section 36 ([30]).
Frequently asked questions
What is the maximum deposit a builder can ask for in SA?
For a domestic building work contract made on or after 1 September 2011 with a price of $20,000 or more, not more than 5% of the price (section 30(4)(d)(ii) of the Building Work Contractors Act 1995). Where the price is under $20,000 and the work is not minor, the limit is $1,000.
Can a builder ask for a 10% deposit in South Australia?
Not on a domestic building work contract to which section 30 applies. The limit is 5% of the price, and demanding more is an offence with a maximum fine of $100,000 for an individual or $500,000 for a company.
Does the 5% deposit limit apply to jobs under $20,000?
No. For contracts made on or after 10 November 2025, work costing the owner less than $20,000 is minor domestic building work, and section 30 does not apply to it (section 27(2)).
Can a builder charge for plans and engineering before the contract?
A payment to a third party for engineering, drawing, surveying or other professional services is a prescribed payment (section 30(4)(a)). The contractor’s own design fees sit outside that paragraph on its words and need to fit within another part of section 30.
When can a builder ask for a progress payment?
Only for work already performed, as a genuine progress payment (section 30(1)(a)), and the owner need not pay unless the contractor has requested the payment by written notice (section 30(3)), unless the Security of Payment Act applies.
Does the Security of Payment Act apply to home renovations?
Not where the domestic building work is on the part of premises the owner resides in or proposes to reside in (section 7(2)(b)). It can apply to domestic building work for owners who do not live there, and it applies to subcontracts and commercial construction contracts.
What is a payment claim in SA?
A claim under section 13 of the Security of Payment Act that identifies the work it relates to, states the amount claimed and states that it is made under the Act. A respondent that does not give a payment schedule in time becomes liable for the claimed amount (section 14).
Is a payment claim the same as an invoice?
Not always. An invoice becomes a payment claim under the Security of Payment Act only if it meets section 13, including the statement that it is made under the Act.
Can an owner withhold payment for defective work?
A domestic building work contract usually deals with this in its payment and defects clauses. Where the Security of Payment Act applies, the respondent must set out its reasons for paying less than the claimed amount in a payment schedule within time (section 14). Disputes about defects in domestic building work can go to the Magistrates Court under section 37.
Do I need a lawyer to set up building payment terms?
The law does not require one. We draft deposit and stage payment terms that meet section 30, and payment claim terms for the jobs where the Security of Payment Act applies.