Retaining Wall Builder Terms and Conditions SA: Retaining Wall Contracts
Retaining wall builder terms and conditions in South Australia
A retaining wall holds back the ground on one side and, on a boundary, the neighbour on the other. The Building Work Contractors Act 1995 (SA) treats a wall as building work, the planning rules draw an approval line at 1 metre of retained ground, and excavation near a boundary can bring in a notice to the neighbour. The contract has to say where the wall goes, who designed it and what happens when the ground is not what the quote assumed. Talon Legal drafts retaining wall builder terms and conditions, retaining wall contracts and subcontracts for South Australian retaining wall, sleeper wall and block wall businesses. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Retaining wall builder terms and conditions SA key facts
| Issue | Position for retaining wall builders in South Australia |
|---|---|
| Governing law | Building Work Contractors Act 1995 (SA) and Regulations 2026; Planning, Development and Infrastructure Act 2016 (SA) and its General Regulations 2017; Work Health and Safety Regulations 2012 (SA); Building and Construction Industry Security of Payment Act 2009 (SA). Current to 21 November 2026. |
| Walls as building work | A building includes a wall or structure, so building a retaining wall is building work (section 3). |
| At a house | Building work within the curtilage of a house or on its boundary is domestic building work (regulation 4(2)(b)). |
| The 1 metre line | A wall retaining a difference in ground levels of no more than 1 metre is declared not to be development, outside designated flood areas and more than 100 metres from the coast (General Regulations Schedule 4 clause 4(1)(f)). |
| $20,000 or more | The Division 1 contract with Form 1, a deposit of no more than 5% and cooling-off (sections 28, 30, 36); insurance where approval is needed (sections 33(2), 34). |
| The neighbour | Excavation and fill near a boundary can be work treated as affecting the stability of the neighbour's land (Planning, Development and Infrastructure Act section 139; regulation 64). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need retaining wall builder terms and conditions? What this guide covers
This guide covers what is particular to retaining wall builder terms and conditions in South Australia, current to 21 November 2026. It deals with the licence and the $20,000 line, the approval line at 1 metre, the wall’s position and the boundary, the neighbour, engineering, drainage and ground, and payment. The rules every structural trade shares are in the concrete and masonry contracts SA guide.
We act for retaining wall builders who work for owners, builders and developers, and for landscapers who build walls.
Free Consultation. Send us the quote and terms you use now. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- The licence and the $20,000 line
- The 1 metre approval line
- Where the wall goes: position and boundary
- Neighbours, excavation and fill
- Engineering, drainage and ground
- Completion and payment
- What the retaining wall pack holds
- How similar matters tend to play out
- Retaining wall case law
- How we build retaining wall builder terms and conditions
- Frequently asked questions
- Related trade contract guides
The licence and the $20,000 line
A building includes a wall or structure (section 3), so building a retaining wall for others is performing building work and needs a licence (section 6(1)). A licence can be limited to specified building work (Schedule 1 Part 3 clause 3(d)). A landscaper or concreter that adds walls to its work should check its licence covers them before quoting.
| Retaining wall job | Rules |
|---|---|
| A wall at a house under $20,000 | Minor domestic building work: the statutory warranties in section 32 apply; Division 1 does not (section 27(2); regulation 4(4)) |
| The same job at $20,000 or more | Division 1: a written contract with every term, licence details, signatures and Form 1 (section 28), a fixed price (section 29), a deposit of no more than 5% (section 30(4)), cooling-off (section 36) |
| A wall that needs development approval, at $20,000 or more | Building indemnity insurance in force, and the certificate given, before work starts (sections 33(2), 34) |
| Walls for a builder or developer | A subcontract or commercial contract; the Security of Payment Act |
A variation is part of the contract (section 3). A wall that grows once the levels are set out can take a job over $20,000 and over the approval line at the same time.
The 1 metre approval line
Development includes building work (Planning, Development and Infrastructure Act 2016 section 3(1)), and the General Regulations declare some work not to be development (regulation 3C). They declare that a retaining wall retaining a difference in ground levels of no more than 1 metre is not development (Schedule 4 clause 4(1)(f)). The exclusion does not apply in designated flood areas or within 100 metres of the coast, or to a State heritage place (regulation 3C(3)).
Two more lines matter where a fence sits on top of the wall. A fence of up to 2.1 metres is excluded subject to exceptions, and a masonry fence, or a fence partly of masonry, over 1 metre is one of them (clause 4(1)(d)).
The terms should say:
| Term | What it settles |
|---|---|
| Retained height | The difference in ground levels the wall will retain, measured on the plan |
| Approval | Whether the wall needs approval, who applies, and that work waits for it |
| Insurance | Whether building indemnity insurance applies, following the approval answer |
| Height change | That a change in retained height is a variation, and that a wall that crosses the line stops for approval |
In Ong, below, a wall approved to 3 metres was built to 3.6 metres when the site conditions required it, and the council later granted retrospective approval ([134]). A contract that stops for approval when the height changes avoids that position.
Where the wall goes: position and boundary
A wall near a boundary raises two questions: where the boundary is, and which side of it the wall sits. In Ong, the owner said the wall should have straddled the boundary with the neighbour. The Magistrate found that was not a term of the contract, partly because the contract documents did not specify a location for the wall ([11]). The contractor’s terms put “correct survey marks, boundary/retaining wall locations” on the owner ([126]). The owner had a survey but had not given it to the contractor ([129]), and the site supervisor set out the wall from the old brush fence ([130]). The engineer’s documents said the boundaries had not been checked ([146]).
The terms should record:
- the boundary used for set-out, and who provided it;
- whether a survey is required, and who obtains and pays for it;
- the wall’s position against the boundary, drawn on the plan;
- whether the neighbour has agreed to a shared wall, in writing; and
- that the builder does not warrant the boundary unless it set it out from a survey.
The fencer guide deals with dividing fences on top of boundary walls and the Fences Act.
Neighbours, excavation and fill
Cutting into a slope or filling behind a wall close to a boundary can be work the General Regulations treat as affecting the stability of the neighbour’s land. That includes an excavation that intersects a plane sloping down at 1 vertical to 2 horizontal from a point 600 mm below natural ground level at the boundary (regulation 64(2)(a)). It also includes fill within 600 mm of an adjoining site, other than fill of no more than 200 mm for gardening or similar purposes (regulation 64(2)(c)).
Where a development approval envisages that the person undertaking the work will need access to the neighbour’s land to deal with an effect on its stability, section 139 applies. A notice in the prescribed form must be served on the neighbour at least 20 business days before the work starts (section 139(2)(a); regulation 64(2a)). The neighbour may require the building owner to shore up any excavation, or to underpin, stabilise or otherwise strengthen the foundations of any building, to the extent its professional engineer specifies (regulation 64(3)).
The contract should say who serves the notices and who pays for work the neighbour requires. Excavation also brings the safety rules: before excavation starts, the person with management or control of the workplace must take all reasonable steps to obtain current underground essential services information (Work Health and Safety Regulations 2012 regulation 304(2)).
Engineering, drainage and ground
A wall fails when the ground behind it moves or the water behind it has nowhere to go. The statutory warranties require the work to be performed in a proper manner to accepted trade standards and the agreed plans and specifications (section 32(2)(a)). Where the owner relies on the builder’s skill and judgment for a purpose made known, such as holding back a cut for a house pad, the work must be fit for that purpose (section 32(2)(f)).
| Term | What it settles |
|---|---|
| Design | The engineer, the drawings and revision, or the manufacturer's design tables for a block system |
| Post spacing and footings | Spacing, depth and footing sizes as designed, with any change signed off by the engineer |
| Drainage | Agricultural drain, gravel backfill, weep holes and the discharge point |
| Ground conditions | What the price assumes about clay, rock, fill and water, and how extra work is priced |
| Surcharge | Driveways, pools, sheds or slopes above the wall that the design allowed for |
In Vettese, below, a council had approved a retaining wall, but the walls built were not to the specifications in the approved application ([2]). An engineer gave evidence that the walls were not generally structurally adequate, apart from sections where the post spacing was as originally specified ([53]).
A person who buys or otherwise acquires a house succeeds to the previous owner’s rights under the statutory warranties (section 32(3)), and proceedings must be brought within five years after completion of the work (section 32(5)).
Completion and payment
For a homeowner job of $20,000 or more, the builder must not demand payment unless it is a genuine progress payment for work already performed, a prescribed payment such as a deposit of no more than 5%, or an entitlement under the Security of Payment Act (section 30(1), (2a), (4)).
Final payment is a point where retaining wall disputes arise. In Ong, the contract made full payment due on completion. The Magistrate found the works practically complete when the owner could use them for their intended purpose, despite minor defects that did not impair the integrity of the work, and found no obligation to obtain a certificate of completion before payment ([142]). Parker J called that a completely orthodox and correct application of the principle of practical completion ([143]).
Walls for builders and developers fall under the Security of Payment Act, and excavation and other operations preparatory to building work are construction work (section 5(1)(e)(i)). A payment claim must identify the work, state the amount and say it is made under the Act (section 13(2)).
What the retaining wall pack holds
A retaining wall pack is built from our masters and a retaining wall schedule, and quoted as a fixed fee before we start.
- Homeowner terms for jobs under $20,000 and a domestic building work contract with Form 1 for larger jobs.
- A set-out and boundary sheet recording the boundary used, any survey and the wall’s position.
- An approvals clause tied to the retained height, with a stop for approval if the height changes.
- A neighbour notice and access clause that follows section 139 and regulation 64.
- A design, drainage and ground conditions sheet, and a completion and handover form.
- A subcontract with payment claim and schedule procedures for work for builders and developers.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Every job turns on its own contract and facts.
The wall that crossed the line. A sleeper wall is quoted at 900 mm of retained height. Set-out shows the cut is deeper at one end, and the wall will retain 1.3 metres there. The contract treats the change as a variation and stops that section for approval.
The boundary nobody checked. A builder sets out a block wall from an old paling fence. A later survey puts the boundary 150 mm away. The contract recorded that the owner provided the boundary and that no survey was obtained, so the question is the owner’s.
The neighbour’s notice. A cut for a house pad comes within 1 metre of the side boundary and will need access to the neighbour’s land to shore it. The approval envisages that access. The builder’s start date waits for the notice period, and the contract records that the owner serves it.
Retaining wall case law
None of the decisions below set a standard for every retaining wall; each turned on its own contract and facts. Both concerned walls at houses.
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Ong v Adelaide Retaining Walls [2022] SASC 37 | Supreme Court | The wall's location was not a contract term where the documents did not specify it; the contractor was entitled to payment at practical completion | [10], [11], [126], [142], [143], [180] |
| Vettese v Kemp [2000] SASC 154 | Supreme Court (Full Court) | Vendors who built a house owed its buyers a duty of care, breached by the failure to construct a proper retaining wall | [1], [2], [53], [56], [57], [82], [94] |
Case notes
Ong v Adelaide Retaining Walls [2022] SASC 37
A retaining wall business built a wall and fence between an owner’s land and her neighbour’s, and excavation, retaining and terracing works elsewhere on the site ([6]). The Magistrate gave the contractor judgment for $67,176.67, after a set-off of $2,900 for rectification, and found payment fell due on substantial completion ([10]). The Magistrate found it was not a term that the wall straddle the boundary, because the contract documents did not specify a location and the wall’s position matched the engineering documents ([11]). On appeal, Parker J found the Magistrate’s approach to practical completion orthodox and correct ([143]), and found no error in the conclusion that there was no breach of contract because two of the walls had not been approved before they were built ([137]). The appeal was dismissed on all grounds ([180]).
Vettese v Kemp [2000] SASC 154
The buyers of a sloping Wynn Vale block bought from vendors, one of them a licensed builder who helped build the house ([1]). Rock fell from the embankment behind the house, and the sleeper wall buckled. The wall had not been built to the specifications in the application the council had approved ([2]). Duggan J, with whom Bleby J agreed, found that the vendors owed the buyers a duty of care and breached it by failing to construct a proper retaining wall ([56], [94]). The finding of negligence was upheld ([57]), and the damages were reduced by $7,050, for a verandah roof, to $47,772 ([82]).
How we build retaining wall builder terms and conditions
We start with how you quote, set out and build: who designs, who finds the boundary, and who you work for.
| Stage | What happens | What we do |
|---|---|---|
| 1. Intake | A questionnaire on your licence, wall types, heights, engineers and clients | We sort your jobs by retained height, approval and contract type |
| 2. Review | Your quotes, terms, set-out sheets and variation forms | We mark the boundary, approval and payment terms that leave you exposed |
| 3. Drafting | Masters and the retaining wall schedule | We draft homeowner terms, a contract for larger jobs, set-out and neighbour forms and a subcontract |
| 4. Delivery | Word documents ready for quoting | We brief your crew leaders on set-out, height changes and handover |
We cannot promise that terms prevent every dispute. Terms that fix the boundary, the height and the design before the first post goes in settle those questions before they reach the neighbour.
Before your next wall quote goes out. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Frequently asked questions
Do retaining wall builders need a builders licence in SA?
Yes. A building includes a wall or structure, so building a retaining wall for others is building work, and carrying on that business needs a licence (Building Work Contractors Act 1995 sections 3, 6(1)).
Does a retaining wall need development approval?
A wall retaining a difference in ground levels of no more than 1 metre is declared not to be development, outside designated flood areas and more than 100 metres from the coast (Planning, Development and Infrastructure (General) Regulations 2017 Schedule 4 clause 4(1)(f)). A higher wall is outside that exclusion.
Does a retaining wall job need a written contract?
At a house, for $20,000 or more, yes: a contract that meets section 28 of the Building Work Contractors Act 1995, given with Form 1. Under $20,000, the statutory warranties in section 32 still apply.
Who is responsible for finding the boundary?
The contract decides. In Ong, the contractor’s terms put survey marks and boundary and wall locations on the owner, and the location was not a term where the documents did not specify it.
Does a boundary wall need a notice to the neighbour?
It can. Where excavation or fill near the boundary is work the regulations treat as affecting stability, and the approval envisages access to the neighbour’s land, a notice in the prescribed form is due 20 business days before work starts (Planning, Development and Infrastructure Act section 139; regulation 64).
Can a neighbour require shoring or underpinning?
Where section 139 applies, yes. The neighbour may require the building owner to shore up any excavation, or to underpin, stabilise or otherwise strengthen the foundations of any building, to the extent its professional engineer specifies (General Regulations regulation 64(3)).
Is a retaining wall builder liable to a later owner?
It can be. A person who acquires a house succeeds to the previous owner’s rights under the statutory warranties, and proceedings must start within five years after completion (Building Work Contractors Act section 32(3), (5)). In Vettese, the vendors who built a house were found liable in negligence to its buyers for an inadequate retaining wall.
When is final payment due on a retaining wall?
When the contract says. In Ong, payment fell due at practical completion, when the owner could use the works for their purpose, despite minor defects.
How much deposit can a retaining wall builder take?
For a homeowner job of $20,000 or more, no more than 5% of the price. Later payments can only be genuine progress payments for work already performed (Building Work Contractors Act section 30(1), (4)).
Do I need a lawyer for retaining wall builder terms and conditions?
The law does not require one, but retaining wall terms have to work with the builders licence rules, the approval line, the neighbour provisions and the statutory warranties. We draft retaining wall builder terms and conditions for South Australian wall builders that fix the boundary and the height on paper.
Related trade contract guides
Related guides
- Concrete and masonry contracts SA
- Underpinning contractor terms and conditions SA
- Concreter terms and conditions SA
- Landscaper terms and conditions SA
- Fencer terms and conditions SA
- Minor domestic building work under $20,000
- Statutory warranties and defects
- Variations to a building contract
- Builders licence SA
- Trade contracts SA