Concreter Terms and Conditions SA: Slab, Footing and Concreting Contracts
Concreter terms and conditions in South Australia
A concreter builds to someone else’s design, on ground nobody has fully seen, with a product that sets on a deadline. The Building Work Contractors Act 1995 (SA) treats slabs and footings as building work, so the licence, the homeowner contract rules and the statutory warranties all apply. The contract decides the rest: who designed the slab, what the site was assumed to be, and how extra concrete is measured and paid. Talon Legal drafts concreter terms and conditions, concreting contracts and subcontracts for South Australian concreters and concrete contractors. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Concreter terms and conditions SA key facts
| Issue | Position for concreters in South Australia |
|---|---|
| Governing law | Building Work Contractors Act 1995 (SA) and Regulations 2026; Building and Construction Industry Security of Payment Act 2009 (SA); Work Health and Safety Regulations 2012 (SA); Australian Consumer Law. Current to 21 November 2026. |
| Slabs and footings | Building work: constructing a building, and excavating or filling a site for it (section 3). |
| At a house | Domestic building work within the curtilage of a house or on its boundary (regulation 4(2)(b)). |
| $20,000 or more | The Division 1 contract with Form 1, a deposit of no more than 5% and cooling-off (sections 28, 30, 36); under $20,000 the statutory warranties still apply (section 32). |
| Insurance | Building indemnity insurance before work starts, where the work needs development approval and is not minor work (sections 33(2), 34). |
| Work for builders | Laying foundations is construction work, so payment claims are available (Security of Payment Act section 5(1)(e)(ii)). |
| First step | Same-day free 30-minute consultation. Call (08) 7094 2021. |
Need concreter terms and conditions? What this guide covers
This guide covers what is particular to concreter terms and conditions in South Australia, current to 21 November 2026. It deals with the licence and the $20,000 line, building to an engineer’s design, site conditions, pours and delivery dockets, cracking and handover, and work for builders. The rules every structural trade shares are in the concrete and masonry contracts SA guide.
We act for concreters who pour house slabs and footings for owners and builders, and concrete contractors on commercial sites.
Free Consultation. Send us the quote, terms or subcontract you use now. Book a same-day free 30-minute consultation or call (08) 7094 2021.
On this page
- The licence and the $20,000 line
- Building to the engineer's design
- Site conditions, excavation and services
- Pours, pumps and delivery dockets
- Cracking, curing and handover
- Work for builders: variations and back charges
- What the concreting pack holds
- How similar matters tend to play out
- Concreting case law
- How we build concreter terms and conditions
- Frequently asked questions
- Related trade contract guides
The licence and the $20,000 line
Constructing a building is building work, and so is excavating or filling a site for that work (section 3). A concreting business that performs building work for others needs a licence (section 6(1)). A licence can be limited to specified building work (Schedule 1 Part 3 clause 3(d)), so a concreter should check that its licence covers each kind of work it quotes, such as a retaining wall or a garage slab with a footing beam.
| Concreting job | Rules |
|---|---|
| A slab, path or footing at a house under $20,000 | Minor domestic building work: the statutory warranties in section 32 apply; Division 1 does not (section 27(2); regulation 4(4)) |
| The same job at $20,000 or more | Division 1: a written contract with every term, licence details, signatures and Form 1 (section 28), a fixed price (section 29), a deposit of no more than 5% (section 30(4)), cooling-off (section 36) |
| A job that needs development approval | Building indemnity insurance in force, and the certificate given, before work starts, unless it is minor work (sections 33(2), 34) |
| Slabs and footings for a builder | A subcontract, not a domestic building work contract (section 3); the Security of Payment Act |
A variation is part of the contract (section 3). An extra slab, a thicker footing or a change of mix can take a job over $20,000, and the contract then has to meet Division 1. In McPherson v Choi, below, the Court noted that no formal written contract was prepared and no insurance policy was carried, contrary to the Act ([6]).
Building to the engineer’s design
House slabs and footings are built to an engineer’s design, which may rely on a soil report. The statutory warranties require the work to be performed in a proper manner, to accepted trade standards and in accordance with the agreed plans and specifications (section 32(2)(a)). Where the owner relies on the contractor’s skill and judgment for a purpose made known, the work must also be fit for that purpose (section 32(2)(f)).
The terms should record:
| Term | What it settles |
|---|---|
| The design | The engineer, the drawing numbers and revision, and the soil report relied on |
| Who engaged the engineer | The owner, the builder or the concreter, and who carries the design if it is wrong |
| Hold points | Inspections before a pour, and who books them |
| Changes on site | That a change to the design needs the engineer's written sign-off and is a variation |
| Owner's instructions | Any instruction the owner insists on against the concreter's written advice |
That last row matters. It is a defence to a warranty claim that the deficiency arose from instructions the owner insisted on contrary to the contractor’s written advice (section 32(7)). The advice has to be in writing.
Site conditions, excavation and services
A footing trench can meet rock, fill, tree roots, water or old services. The price can only allow for what was known when it was given, so the terms should say what the quote assumes and how extra excavation is priced.
- Rock and fill. A rate for rock and for removing unsuitable fill, measured on site and signed off before the extra work is done.
- Services. Before excavation starts, the person with management or control of the workplace must take all reasonable steps to obtain current underground essential services information (Work Health and Safety Regulations 2012 regulation 304(2)). The terms should say who obtains it.
- Deep trenches. For a trench at least 1.5 metres deep, the business must minimise the risk of collapse by shoring, benching or battering, unless a geotechnical engineer advises in writing that the sides are safe (regulation 306(3), (4)).
- The neighbour. A footing excavation close to a boundary can be work treated as affecting the stability of the neighbour’s land, with a notice due 20 business days before work starts where section 139 of the Planning, Development and Infrastructure Act 2016 applies (General Regulations regulation 64). The concrete and masonry guide sets out the rules.
Pours, pumps and delivery dockets
A pour is booked around trucks, pumps, labour and weather. The terms should deal with each.
| Issue | What the terms should say |
|---|---|
| Mix and strength | The specified strength and any additives, as a written term |
| Pump and access | Who books the pump, access for trucks and the pump, and charges for standing time |
| Cancelled pours | Who pays for a pour cancelled by the owner, the builder or the weather |
| Delivery dockets | That the supplier's dockets record the volume delivered, and that copies go to the client |
| Extra concrete | How concrete over the volume on the drawings is measured and priced |
Delivery dockets matter when the volume is disputed. In Contek, below, the Court accepted that the supplier’s dockets proved the volume delivered ([63]), and measured the extra concrete as the delivered volume less an allowance for the volume shown on the contract drawings ([330]). Where a particular strength is agreed, it should be in writing. The decorative concreter guide discusses a driveway case in which a strength agreed in discussions, not in the written quote, was found to be a term of the contract.
Construction work that involves tilt-up or precast concrete is high risk construction work under the Work Health and Safety Regulations (regulation 291(m)). So is construction work in an area of a workplace where powered mobile plant moves (regulation 291(o)). A business carrying out that work must have a safe work method statement prepared before it starts (regulation 299(1)).
Cracking, curing and handover
Where a slab cracks, the dispute is whether the cracking is a defect. The warranties set the standard: proper work to accepted trade standards and the agreed specifications, and good and proper materials (section 32(2)(a), (b)). The terms should not try to exclude those warranties; they can describe the job so the standard is clear.
- Joints. Where control joints go, by drawing or by marked set-out.
- Finish. The finish specified for each area, with a sample or reference where the look matters.
- Curing. Who is responsible for curing after the pour, and for how long.
- After handover. When the slab can take vehicles or loads, and the owner’s part in protecting it.
- Inspection. A handover inspection, signed by the client, recording the condition of the slab.
Proceedings on a statutory warranty must be brought within five years after completion of the work (section 32(5)).
Work for builders: variations and back charges
Slabs and footings for a builder are a subcontract. The laying of foundations is construction work under the Security of Payment Act (section 5(1)(e)(ii)).
- Payment claims. A claim must identify the work, state the amount and say it is made under the Act (section 13(2)).
- Payment schedules. A respondent that does not give a schedule within the contract time, or 15 business days if earlier, becomes liable for the claimed amount (section 14(4)).
- Pay when paid. A clause making payment depend on the head contractor being paid has no effect (section 12).
- Homeowners. The Act does not apply to domestic building work on premises the owner lives in or proposes to live in (section 7(2)(b)).
The subcontract decides how variations are directed and notified. In Contek, the subcontract allowed the scope to be varied only by an express written direction from the superintendent ([263]). A separate clause required notice before varied work started, but the Court found that failing to give it did not bar the claim, because a bar needs express and clear language ([279]); the breach could only sound in damages ([280]). Back charges at the interface with other trades can be shared: the Court allowed half of a patching back charge where the defects arose between the concrete and the formwork contractor’s work ([478], [479]).
What the concreting pack holds
A concreting pack is built from our masters and a concreting schedule, and quoted as a fixed fee before we start.
- Homeowner terms for jobs under $20,000 and a domestic building work contract with Form 1 for larger jobs.
- A design and hold point sheet naming the engineer, the drawings and the soil report.
- A site conditions clause with rates for rock, fill and extra excavation.
- A pour clause for mix, pumps, cancelled pours and delivery dockets.
- A subcontract with payment claim and schedule procedures, written variation directions and back charge notices.
How similar matters tend to play out
These are illustrations built from the rules above, not predictions. Every job turns on its own contract and facts.
The footing that met rock. The quote for a house extension assumed clay. At 400 mm the excavator hits rock along one side. The terms price rock by the cubic metre, measured and signed off before the extra digging, so the variation is recorded and paid.
The extra concrete. A builder disputes a concreter’s claim for 40 extra cubic metres on a commercial slab. The concreter’s subcontract records the delivery dockets as the measure of volume delivered, and the drawings fix the volume the price covered.
The slab the owner wanted lower. An owner insists the slab finish level with the existing path. The concreter advises in writing that it sits too low for the drainage and the owner signs the instruction. When water reaches the slab edge, the written advice is the concreter’s answer under section 32(7).
Concreting case law
None of the decisions below set out a standard form for concreting contracts. Each turned on a point a concreting business can face.
| Case | Court | Principle | Pinpoint |
|---|---|---|---|
| Contek Pty Ltd v Mossop Group Pty Ltd [2024] SADC 1 | District Court | Extra concrete measured by the delivery dockets less the drawings volume; a notice clause without clear words of bar did not defeat a variation claim | [63], [263], [279], [280], [330], [479] |
| McPherson v Choi [2017] SADC 25 | District Court | A concrete garage, steps and driveway built without a written contract or insurance; the work was demolished and rebuilt, and the owner had judgment | [5], [6], [8], [181] |
Case notes
Contek Pty Ltd v Mossop Group Pty Ltd [2024] SADC 1
A concreting subcontractor and a builder disputed variation and back charge claims under two commercial subcontracts. Judge Thomas found that the supplier’s delivery dockets proved the volume delivered for the topping slabs ([63]). Her Honour measured the extra concrete as that delivered volume less a fair and reasonable allowance for the volume measured from the contract drawings ([330]). The subcontract allowed the scope to be varied only by an express written direction ([263]). Failing to give notice before starting varied work did not bar the claim, because the clause contained no language making notice a condition of the entitlement ([279]). Half of a patching back charge was allowed, the defects having arisen at the interface with the formwork contractor’s work ([478], [479]).
McPherson v Choi [2017] SADC 25
A builder contracted to construct a concrete garage, steps and a driveway at an owner’s property, to a building designer’s design and an engineer’s plans ([1], [5]). The Court noted that, contrary to the Building Work Contractors Act, no formal written contract was prepared and no insurance policy was carried ([6]). An engineer concluded the construction was structurally unsound ([8]), and another builder demolished the work and rebuilt the project ([4]). Judge Tracey dismissed the builder’s claim and gave judgment for the owner for $145,871.05 ([181]).
How we build concreter terms and conditions
We start with how you quote, set out and pour: who designs, who supplies the concrete, and who you work for.
| Stage | What happens | What we do |
|---|---|---|
| 1. Intake | A questionnaire on your licence, job sizes, engineers, suppliers and builders | We sort your jobs into minor work, Division 1 contracts and subcontracts |
| 2. Review | Your quotes, terms, pour records and variation forms | We mark the design, site and payment terms that leave you exposed |
| 3. Drafting | Masters and the concreting schedule | We draft homeowner terms, a contract for larger jobs, pour and handover forms and a subcontract |
| 4. Delivery | Word documents ready for quoting | We brief your leading hands on hold points, dockets and variations |
We cannot promise that terms prevent every dispute. Terms that record the design, the site assumptions and the measure of concrete settle those questions before the pour.
Before your next concreting quote goes out. Book a same-day free 30-minute consultation or call (08) 7094 2021.
Frequently asked questions
Do concreters need a builders licence in SA?
Yes, to carry on a business of performing building work for others. Constructing a building, and excavating or filling a site for that work, is building work (Building Work Contractors Act 1995 sections 3, 6(1)).
Does a concreting job need a written contract?
At a house, for $20,000 or more, yes: a contract that meets section 28 of the Building Work Contractors Act 1995, given with Form 1. Under $20,000, the statutory warranties in section 32 still apply.
How much deposit can a concreter take?
For a homeowner job of $20,000 or more, no more than 5% of the price. Later payments can only be genuine progress payments for work already performed (Building Work Contractors Act section 30(1), (4)).
Is a concreter liable for a slab built to the engineer's design?
It depends on whether the work followed the design. The work must be performed in a proper manner and in accordance with the agreed plans and specifications (Building Work Contractors Act section 32(2)(a)). The terms should record who engaged the engineer and which drawings were agreed.
Is a cracked slab a defect?
It depends on the cracking and the specification. The warranties require proper work to accepted trade standards and good and proper materials (Building Work Contractors Act section 32(2)(a), (b)).
Can a concreter rely on the owner's instructions?
It is a defence that a deficiency arose from instructions the owner insisted on contrary to the contractor’s written advice (Building Work Contractors Act section 32(7)). The advice must be in writing.
Who pays for rock found in the footings?
The contract decides. Terms that state what the price assumes and give a rate for rock, measured before the extra work, settle it.
Do delivery dockets prove the volume of concrete?
They can. In Contek, the Court accepted that the supplier’s delivery dockets proved the volume delivered. A subcontract that names the dockets as the measure avoids the argument.
Can a concreter make a payment claim against a builder?
Yes. The laying of foundations is construction work (Security of Payment Act section 5(1)(e)(ii)), so a claim that meets section 13(2) can be served. Domestic building work on a home the client lives in is excluded (section 7(2)(b)).
Do I need a lawyer for concreter terms and conditions?
The law does not require one, but concreting terms have to work with the builders licence rules, the statutory warranties and the payment claim rules. We draft concreter terms and conditions for South Australian concreting businesses that put the design and the site on paper.
Related trade contract guides
Related guides
- Concrete and masonry contracts SA
- Decorative concreter terms and conditions SA
- Retaining wall builder terms and conditions SA
- Underpinning contractor terms and conditions SA
- Garage builder terms and conditions SA
- Minor domestic building work under $20,000
- Statutory warranties and defects
- Variations to a building contract
- Builders licence SA
- Trade contracts SA